Asphalt Tonnage, Tack & Haul
Estimate compacted asphalt tonnage, residual and diluted tack coat volume, paving rate, and haul trucks per round-trip cycle.
- Gross HMA
- 418.6
US tons
- Tack to spray
- 525.4
US gal
- Paver demand
- 217.5
US tons/h
- Haul trucks
- 13
Tack and paver plan view
The sprayed footprint covers the entered mat area. Fleet sizing uses one complete round-trip cycle.
Production and tack screen met
Marker shows plant output relative to paver demand. The tack check uses the selected surface band.
Calculation ledger
- Net compacted HMA
- 398.7 US tons
- Compacted mix density
- 151.01 lb/ft³
- Tack coverage area
- 3,520 yd²
- Route length
- 0.5 mi
- Residual binder volume
- 176 US gal
- Undiluted emulsion volume
- 262.7 US gal
- Diluted distributor bar rate
- 0.149 gal/yd²
- Plant/paver limited throughput
- 217.5 US tons/h
- Fleet at feasible throughput
- 13
- Gross mix supply time
- 1.93 h
- Reference residual tack minimum
- 0.04 gal/yd²
- Reference residual tack maximum
- 0.07 gal/yd²
How the calculation works
- Multiply mat volume by compacted density and add the purchase allowance.
- Convert the required residual binder into supplied emulsion and diluted spray volumes.
- Convert paver travel into mix demand and round truck fleet sizes up.
Check tack rate and dilution against the contract and emulsion supplier. The steady-state haul model assumes uniform payload and cycle time.
Read the equations and sources
Production and tack screen met. Marker shows plant output relative to paver demand. The tack check uses the selected surface band.
Inputs
| Section length | 2,640 ft |
|---|
| Paving width | 12 ft |
|---|
| Compacted thickness | 2 in |
|---|
| Compacted mix SG Gₘᵦ | 2.42 |
|---|
| Purchase allowance | 5% |
|---|
| Receiving surface | Existing asphalt |
|---|
| Residual tack rate | 0.05 gal/yd² |
|---|
| Binder in supplied emulsion | 67% |
|---|
| Added water in final spray | 50% |
|---|
| Plant production | 280 US tons/h |
|---|
| Paver travel speed | 24 ft/min |
|---|
| Truck payload | 22 US tons |
|---|
| Round-trip cycle | 75 min |
|---|
Results
| Gross HMA order | 418.6 US tons |
|---|
| Diluted tack volume | 525.4 US gal |
|---|
| Theoretical paver rate | 217.5 US tons/h |
|---|
| Fleet at requested paver rate | 13 |
|---|
| Net compacted HMA | 398.7 US tons |
|---|
| Compacted mix density | 151.01 lb/ft³ |
|---|
| Tack coverage area | 3,520 yd² |
|---|
| Route length | 0.5 mi |
|---|
| Residual binder volume | 176 US gal |
|---|
| Undiluted emulsion volume | 262.7 US gal |
|---|
| Diluted distributor bar rate | 0.149 gal/yd² |
|---|
| Plant/paver limited throughput | 217.5 US tons/h |
|---|
| Fleet at feasible throughput | 13 |
|---|
| Gross mix supply time | 1.93 h |
|---|
| Reference residual tack minimum | 0.04 gal/yd² |
|---|
| Reference residual tack maximum | 0.07 gal/yd² |
|---|
Check tack rate and dilution against the contract and emulsion supplier. The steady-state haul model assumes uniform payload and cycle time.