Asphalt Tonnage, Tack & Haul

Estimate compacted asphalt tonnage, residual and diluted tack coat volume, paving rate, and haul trucks per round-trip cycle.

Design readout

Gross HMA
418.6
US tons
Tack to spray
525.4
US gal
Paver demand
217.5
US tons/h
Haul trucks
13

Tack and paver plan view

Tack and paver plan viewPAVING PLANTACK COVERAGECOMPACTEDTACKMAT LENGTH2,640 ftMAT WIDTH12 ftSPRAY VOLUME525.4 US gal
The sprayed footprint covers the entered mat area. Fleet sizing uses one complete round-trip cycle.

Production and tack screen met

Marker shows plant output relative to paver demand. The tack check uses the selected surface band.

Calculation ledger
Net compacted HMA
398.7 US tons
Compacted mix density
151.01 lb/ft³
Tack coverage area
3,520 yd²
Route length
0.5 mi
Residual binder volume
176 US gal
Undiluted emulsion volume
262.7 US gal
Diluted distributor bar rate
0.149 gal/yd²
Plant/paver limited throughput
217.5 US tons/h
Fleet at feasible throughput
13
Gross mix supply time
1.93 h
Reference residual tack minimum
0.04 gal/yd²
Reference residual tack maximum
0.07 gal/yd²

Inputs

Changes update results

Compacted mat
ft
ft
in
%
Tack coat
gal/yd²
%
%
Production and haul
US tons/h
ft/min
US tons
min

How the calculation works

  1. Multiply mat volume by compacted density and add the purchase allowance.
  2. Convert the required residual binder into supplied emulsion and diluted spray volumes.
  3. Convert paver travel into mix demand and round truck fleet sizes up.

Check tack rate and dilution against the contract and emulsion supplier. The steady-state haul model assumes uniform payload and cycle time.

Read the equations and sources