ASPHALTPAVELAB / PAVEMENT DESIGN WORKSHEET
One-lane nighttime overlay
Asphalt Tonnage, Tack & Haul · US customary units
Production and tack screen met. Marker shows plant output relative to paver demand. The tack check uses the selected surface band.
Inputs
| Section length | 4,100 ft |
|---|---|
| Paving width | 12 ft |
| Compacted thickness | 1.5 in |
| Compacted mix SG Gₘᵦ | 2.42 |
| Purchase allowance | 4% |
| Receiving surface | Existing asphalt |
| Residual tack rate | 0.05 gal/yd² |
| Binder in supplied emulsion | 67% |
| Added water in final spray | 50% |
| Plant production | 280 US tons/h |
| Paver travel speed | 21 ft/min |
| Truck payload | 19 US tons |
| Round-trip cycle | 48 min |
Results
| Gross HMA order | 482.9 US tons |
|---|---|
| Diluted tack volume | 815.9 US gal |
| Theoretical paver rate | 142.7 US tons/h |
| Fleet at requested paver rate | 7 |
| Net compacted HMA | 464.3 US tons |
| Compacted mix density | 151.01 lb/ft³ |
| Tack coverage area | 5,466.7 yd² |
| Route length | 0.777 mi |
| Residual binder volume | 273.3 US gal |
| Undiluted emulsion volume | 408 US gal |
| Diluted distributor bar rate | 0.149 gal/yd² |
| Plant/paver limited throughput | 142.7 US tons/h |
| Fleet at feasible throughput | 7 |
| Gross mix supply time | 3.38 h |
| Reference residual tack minimum | 0.04 gal/yd² |
| Reference residual tack maximum | 0.07 gal/yd² |
Check tack rate and dilution against the contract and emulsion supplier. The steady-state haul model assumes uniform payload and cycle time.