The mill cut removes existing HMA credit. Required overlay depth is measured from the milled surface.
RAP target supplied on site
Marker compares recovered RAP mass with target RAP demand.
Calculation ledger
Structural number to add
1.56
Pre-mill effective SN
4.226
Retained HMA thickness
5.25 in
New compacted overlay HMA
2,823.3 US tons
RAP to meet target blend
903.5 US tons
RAP stock surplus / shortfall
1,258.7 US tons
On-site RAP in new mix
32%
Virgin binder with on-site stock only
114.22 US tons
Binder savings with full target RAP
35.42 US tons
Inputs
Changes update results
Work through this example
Deduct the milled depth from existing HMA and credit the retained layers.
Convert any structural number deficit to a net overlay thickness.
Compare RAP supply and blend demand, then credit available RAP binder against virgin binder.
Set binder availability to 100% to isolate the mass-balance effect without altering the stockpile tonnage.
The analytical lift is a structural minimum. Confirm practical lift thickness, mix design, binder blending and stockpile processing losses with project data.
Asphalt Overlay Thickness & RAP · US customary units
RAP target supplied on site. Marker compares recovered RAP mass with target RAP demand.
Inputs
Future required SN
5
New HMA coefficient aₒₗ
0.44
Cold-mill removal depth
2.75 in
Rehabilitation area
14,000 yd²
Existing HMA depth
8 in
Intact HMA coefficient
0.44
Retained HMA condition
65%
Existing HMA bulk SG
2.4
Base depth
10 in
Base coefficient
0.14
Retained base condition
85%
Subbase depth
8 in
Subbase coefficient
0.11
Retained subbase condition
85%
New HMA bulk SG
2.43
Target RAP by mix mass
32%
Binder in milled RAP
5.6%
Total new mix binder
5.3%
RAP binder availability
70%
Results
Post-mill effective SN
3.44
Net overlay from milled surface
3.55 in
Recovered milled RAP
2,162.2 US tons
On-site virgin binder savings
35.42 US tons
Structural number to add
1.56
Pre-mill effective SN
4.226
Retained HMA thickness
5.25 in
New compacted overlay HMA
2,823.3 US tons
RAP to meet target blend
903.5 US tons
RAP stock surplus / shortfall
1,258.7 US tons
On-site RAP in new mix
32%
Virgin binder with on-site stock only
114.22 US tons
Binder savings with full target RAP
35.42 US tons
The analytical lift is a structural minimum. Confirm practical lift thickness, mix design, binder blending and stockpile processing losses with project data.