Structural strengthening without milling

Estimate a lift and RAP target when the existing HMA remains in place.

Design readout

Effective SN
3.753
Overlay lift
4.2
in
Milled RAP
0
US tons
Binder saved
0
US tons

Cold-mill and overlay depth section

Cold-mill and overlay depth sectionREHABILITATION SECTIONPOST-MILL DATUMEXISTINGREHABILITATEDMILL CUT0 inRETAINED HMA5.5 inNEW HMA LIFT4.2 in
The mill cut removes existing HMA credit. Required overlay depth is measured from the milled surface.

RAP import or blend change needed

Marker compares recovered RAP mass with target RAP demand.

Calculation ledger
Structural number to add
1.847
Pre-mill effective SN
3.753
Retained HMA thickness
5.5 in
New compacted overlay HMA
2,410.8 US tons
RAP to meet target blend
482.2 US tons
RAP stock surplus / shortfall
-482.2 US tons
On-site RAP in new mix
0%
Virgin binder with on-site stock only
130.18 US tons
Binder savings with full target RAP
24.11 US tons

Inputs

Changes update results

Structure and mill depth
in
yd²
Existing asphalt
in
%
Existing granular support
in
%
in
%
New blend mass balance
%
%
%
%

Condition percentages multiply the intact layer coefficients. Set them using field condition and agency guidance.

Work through this example

  1. Deduct the milled depth from existing HMA and credit the retained layers.
  2. Convert any structural number deficit to a net overlay thickness.
  3. Compare RAP supply and blend demand, then credit available RAP binder against virgin binder.

Recovered stock and on-site binder savings are zero. The target still estimates required imported RAP.

The analytical lift is a structural minimum. Confirm practical lift thickness, mix design, binder blending and stockpile processing losses with project data.

Read the equations and sources