Two-inch mill and structural lift

Compare retained SN and binder recovery for a moderate mill ahead of structural strengthening.

Design readout

Effective SN
3.416
Overlay lift
4.05
in
Milled RAP
1,404
US tons
Binder saved
31.69
US tons

Cold-mill and overlay depth section

Cold-mill and overlay depth sectionREHABILITATION SECTIONPOST-MILL DATUMEXISTINGREHABILITATEDMILL CUT2 inRETAINED HMA5.25 inNEW HMA LIFT4.05 in
The mill cut removes existing HMA credit. Required overlay depth is measured from the milled surface.

RAP target supplied on site

Marker compares recovered RAP mass with target RAP demand.

Calculation ledger
Structural number to add
1.784
Pre-mill effective SN
3.98
Retained HMA thickness
5.25 in
New compacted overlay HMA
2,881.2 US tons
RAP to meet target blend
633.9 US tons
RAP stock surplus / shortfall
770.1 US tons
On-site RAP in new mix
22%
Virgin binder with on-site stock only
123.89 US tons
Binder savings with full target RAP
31.69 US tons

Inputs

Changes update results

Structure and mill depth
in
yd²
Existing asphalt
in
%
Existing granular support
in
%
in
%
New blend mass balance
%
%
%
%

Condition percentages multiply the intact layer coefficients. Set them using field condition and agency guidance.

Work through this example

  1. Deduct the milled depth from existing HMA and credit the retained layers.
  2. Convert any structural number deficit to a net overlay thickness.
  3. Compare RAP supply and blend demand, then credit available RAP binder against virgin binder.

Change only milling depth. Effective SN falls while recovered RAP rises.

The analytical lift is a structural minimum. Confirm practical lift thickness, mix design, binder blending and stockpile processing losses with project data.

Read the equations and sources