Worked example
Basement stair takeoff for a 108 in rise
A straight basement flight rises 108 in to an existing landing. It uses a 7 in perpendicular waist and a 42 in clear planning width.
Estimate
Concrete to order
- Entered dimensions meet the basic straight residential stair screen. Verify adopted code, clear widths, headroom, nosings and landings.
- Order volume · equivalent
- 1.273 m³
- 80 lb bags
- 75
- Riser count
- 14
- Treads before landing
- 13
- Actual rise per step
- 7.714 in
- Horizontal flight run
- 11.38 ft
- Run including landing
- 11.38 ft
- 2R + T comfort check
- 25.93 in
- Slope angle
- 36.3 °
- Waist volume
- 1.067 yd³
- Step wedge volume
- 0.474 yd³
- Landing volume
- 0 yd³
- Net concrete
- 1.541 yd³
Download
Working this example
Starting estimate 1.665 yd³Concrete to order
Measure headroom to the structure above the nosing line. The run calculation alone does not evaluate the opening.
Questions & answers
How many risers does the 108 in basement rise need?
108 ÷ 7.75 rounds up to 14 equal risers. Each riser is about 7.714 in.
Do I add concrete for an existing basement landing?
Leave the landing depth at zero when the landing already exists and the work covers the new flight.