Worked example
Bags for six round deck piers
A deck takeoff includes six round forms with 18 in internal diameter and 4 ft fill height. The bag estimate includes a 12% allowance.
Estimate
Concrete to order
- Confirm packaged yield, truck capacity and minimum order with your supplier.
- Order volume · equivalent
- 1.345 m³
- Net volume
- 1.571 yd³
- Estimated wet weight
- 3.44 short ton
- Wet weight · equivalent
- 3.12 t
- 40 lb bags
- 159
- 60 lb bags
- 106
- 80 lb bags
- 80
- Ready-mix loads
- 1
- Volume in last truck
- 1.759 yd³
Download
Working this example
Starting estimate 1.759 yd³Concrete to order
Measure a flared base separately. The round column model uses a constant inside diameter.
Questions & answers
Should a pier tube be measured by inside or outside diameter?
Use the inside diameter that concrete fills. The area changes with the square of the diameter.
How do I take off a widened base under these deck piers?
Split the shape into the cylindrical shaft and the base below it. Add their volumes before choosing an order allowance.