Bags for six round deck piers

A deck takeoff includes six round forms with 18 in internal diameter and 4 ft fill height. The bag estimate includes a 12% allowance.

Inputs

Measurement system
ft
in
%
lb/ft³
Used for the wet concrete weight estimate.
CONCRETE POUR SECTIONPour geometry at left and the estimated last truck load at right. CONCRETE POUR SECTION 18 in4 ft high · 6 poursREADY-MIX LOADS1 × 10 yd³ capacityLast load 1.76 yd³

Estimate

Concrete to order
1.759 yd³
  • Confirm packaged yield, truck capacity and minimum order with your supplier.
Order volume · equivalent
1.345 m³
Net volume
1.571 yd³
Estimated wet weight
3.44 short ton
Wet weight · equivalent
3.12 t
40 lb bags
159
60 lb bags
106
80 lb bags
80
Ready-mix loads
1
Volume in last truck
1.759 yd³
Download

Working this example

Starting estimate 1.759 yd³Concrete to order

Measure a flared base separately. The round column model uses a constant inside diameter.

See the calculator formulas and assumptions

Questions & answers

Should a pier tube be measured by inside or outside diameter?

Use the inside diameter that concrete fills. The area changes with the square of the diameter.

How do I take off a widened base under these deck piers?

Split the shape into the cylindrical shaft and the base below it. Add their volumes before choosing an order allowance.