ConcreteEarthLab

Worked example

Ready-mix for a metric strip footing

A straight footing section is 28 m long, 600 mm wide and 250 mm deep. The estimator adds a 7% allowance to the formed quantity.

Inputs

Measurement system
m
m
mm
%
kg/m³
Used for the wet concrete weight estimate.
CONCRETE POUR SECTIONPour geometry at left and the estimated last truck load at right. CONCRETE POUR SECTION 28 m250 mm thick · 1 pourWidth 0.6 mREADY-MIX LOADS1 × 7.65 m³ capacityLast load 4.49 m³

Estimate

Concrete to order
4.494 m³
  • Confirm packaged yield, truck capacity and minimum order with your supplier.
Order volume · equivalent
5.878 yd³
Net volume
4.2 m³
Estimated wet weight
10.44 t
Wet weight · equivalent
11.51 short ton
40 lb bags
530
60 lb bags
353
80 lb bags
265
Ready-mix loads
1
Volume in last truck
4.494 m³
Download

Working this example

Starting estimate 4.494 m³Concrete to order

Check foundation intersections against the plan so two measured runs share their crossing volume only once.

See the calculator formulas and assumptions

Questions & answers

What is the net volume of the 28 m strip footing?

28 × 0.60 × 0.25 gives 4.20 m³ of concrete before the allowance.

When should strip footing lengths be broken into sections?

Break at changes in width, elevation or depth. Measure steps and widened pads as their own sections.