Worked example
Ready-mix for a metric strip footing
A straight footing section is 28 m long, 600 mm wide and 250 mm deep. The estimator adds a 7% allowance to the formed quantity.
Estimate
Concrete to order
- Confirm packaged yield, truck capacity and minimum order with your supplier.
- Order volume · equivalent
- 5.878 yd³
- Net volume
- 4.2 m³
- Estimated wet weight
- 10.44 t
- Wet weight · equivalent
- 11.51 short ton
- 40 lb bags
- 530
- 60 lb bags
- 353
- 80 lb bags
- 265
- Ready-mix loads
- 1
- Volume in last truck
- 4.494 m³
Download
Working this example
Starting estimate 4.494 m³Concrete to order
Check foundation intersections against the plan so two measured runs share their crossing volume only once.
Questions & answers
What is the net volume of the 28 m strip footing?
28 × 0.60 × 0.25 gives 4.20 m³ of concrete before the allowance.
When should strip footing lengths be broken into sections?
Break at changes in width, elevation or depth. Measure steps and widened pads as their own sections.