Scope and decisions
These calculators cover static heavy-lift planning and machinery moves. Confirm weight, center of gravity, gear ratings, crane configuration and ground support for each lift phase. A qualified person owns the lift plan and decides when engineering review is needed.
A utilization of 100% means the calculation reached the entered comparison value. The 75% tandem chart cap is a planning assumption on this site. OSHA 1926.1432 separately requires a qualified-person plan for covered multiple-crane lifts. The two-leg rigid-load option is a conservative screen to apply alongside the ASME B30.9 assembly rating and the manufacturer’s instructions.
Units and rounding
The models use SI internally. Entered weight labels in lb, US tons, kg and metric tonnes are mass-equivalent, based on standard gravity of 9.80665 m/s². US short tons contain 2,000 lb and metric tonnes contain 1,000 kg. Force outputs use lbf or kN. The line-force and bearing checks use unrounded values.
Model limitations
Sling Tension & Hitch WLL
Compare with the tagged assembly WLL for the actual material, hitch, angle, number of legs, fittings and bend radius. Use the lower approved limit. Have a qualified person verify load sharing and the assumptions for rigid loads.
Asymmetric CG & Sling Tension
For two angled legs, use one plane and the declared attitude. The four-pickup bounds apply to vertical reactions on a level rectangle. The individual maxima are separate equilibrium cases. Verify line geometry, load stability, pickup strength and tagged WLL with a qualified rigger.
Crane Outrigger Ground Bearing
Use a verified geotechnical bearing value and OEM outrigger reactions. Have pad or mat strength, effective bearing, settlement, slope, underground services and voids checked separately.
Tandem Crane Load Sharing
Use the weakest chart point at each actual radius, boom configuration and set-up. A qualified person must plan the lift under OSHA 1926.1432 where it applies. This is a static snapshot for vertical lines. Review dynamic load transfer and any off-plumb line separately.
Wire Rope Reeving & Fleet Angle
Compare line pull with the OEM winch rating at the working drum layer and confirm compatible reeving, rope construction, termination efficiency and sheave sizing. A 3.5:1 design factor requires equipment- and use-specific review under the applicable OSHA provisions.
Spreader Bar vs. Lifting Beam
Use a rated device or a design verified to ASME BTH-1 and B30.20. The axial comparison uses a structural-steel flexural model only. Review slender walls, eccentricity, lateral instability, welds, fatigue, hardware and applicable device design factors separately.
Crane Wind Load & Sway
Estimate steady payload drag only. Use the crane manufacturer’s instructions and load-specific wind limit. This model excludes transient motion, the boom’s own wind loading and ASCE 7 exposure and gust factors.
Machinery Skidding & Winch Pull
Use measured or reviewed friction values. Confirm the working-layer winch rating, anchor load path, braking, surface integrity and route geometry with a qualified team. Snagging, side pulls and transient forces can govern.
Standards and primary references
Consult the applicable edition, manufacturer documentation and site procedures for the job. The linked publisher pages describe the standards’ scope. The lift screens use the assumptions above and on each worksheet.
- ASME B30.5 | Mobile and Locomotive Cranes
- ASME B30.9 | Slings
- ASME B30.20 | Below-the-Hook Lifting Devices
- ASME BTH-1 | Design of Below-the-Hook Lifting Devices
- AISC 360 | Round-section flexural buckling reference, Chapter E
- OSHA 1926.251 | Rigging equipment for material handling
- OSHA 1926.1400 | Scope of Cranes and Derricks in Construction
- OSHA 1926.1402 | Ground conditions
- OSHA 1926.1414 | Wire rope selection
- OSHA 1926.1417 | Operation and weather
- OSHA 1926.1432 | Multiple-crane lifts
- OSHA sling guidance | Wire-rope choke-angle table, Fig. 2
- WSH Council crane guide | Rigid loads and multi-leg slings
- CERTEX | Drum fleet-angle guidance
- ASCE 7 | Wind loads for buildings and other structures
- Liebherr | Influence of wind on crane operation