EcomMarginLab

Inventory · Worked example

EOQ and safety stock for bicycle repair parts

Calculate reorder point and cash buffer in Canadian dollars for imported bicycle repair kits with a long, variable replenishment lead time.

Scenario note. Rerun the forecast with a faster domestic supplier. Its higher unit cost may change holding expense while shorter lead times reduce the reorder buffer.

Edit this example

Results ↓
CAD C$

Inputs

Demand and lead time
16
7
36
8
99% · Z 2.326
Purchasing and carrying cost
C$ C$137
C$ C$18.5
% 25%

Estimate

Reorder point (units)
890
Safety stock (units)
314
Economic order quantity
588
Stock on hand through the order cycle
Stock on hand through the order cycleOn-hand inventory falls from 902 units to safety stock of 314 units. The reorder point uses inventory position and is 890 units.Units on handROP uses inventory position05321.1kROP 890Safety stock 314036.7573.5Time since first receipt · days
Service level Z-score
2.33
Annual demand
5,840
Expected lead-time demand
576
Lead-time demand standard deviation
134.71
Annual holding cost per unit
C$4.63
Optimal orders per year
9.93
Average units on hand
608
Average days on hand
38 days
Days between orders
36.75 days
Cash in safety stock
C$5,809.00

How this estimate works

Assume daily demand is independent across days and independent of supplier lead time. Allow for both sources of variation and use a normal approximation to size the stock buffer. Round safety stock and the reorder point up to whole units.

Use inventory position to trigger the reorder: units on hand plus units on order, less backorders. The chart shows on-hand units under steady consumption and instant receipt. Several purchase orders can be open at once.

EOQ balances order setup and holding costs over 365 days. The result compares the whole quantities around the continuous optimum. Review carton multiples, supplier minimums, capacity, and seasonality separately.

View the full methodology

Frequently asked questions

What portion of the repair kit buffer comes from lead time?

Set lead-time variation to zero while keeping demand variation unchanged. Compare that buffer with the original calculation to see the combined effect.

Will the bicycle kit buffer account for multi-item shortages?

Treat this as a single stock-keeping unit. Plan unavailable components and any substitution rules separately.