Inventory EOQ, reorder point and safety stock calculator

Set when to reorder, how much to buy, and how much cash to keep in reserve stock.

Estimate your numbers

Results ↓
USD $

Inputs

Demand and lead time
32
9
24
4
95% · Z 1.645
Purchasing and carrying cost
$ $75
$ $8.5
% 24%

Estimate

Reorder point (units)
991
Safety stock (units)
223
Economic order quantity
927
Stock on hand through the order cycle
Stock on hand through the order cycleOn-hand inventory falls from 1.2k units to safety stock of 223 units. The reorder point uses inventory position and is 991 units.Units on handROP uses inventory position06791.4kROP 991Safety stock 223028.9757.94Time since first receipt · days
Service level Z-score
1.64
Annual demand
11,680
Expected lead-time demand
768
Lead-time demand standard deviation
135.38
Annual holding cost per unit
$2.04
Optimal orders per year
12.6
Average units on hand
686.5
Average days on hand
21.45 days
Days between orders
28.97 days
Cash in safety stock
$1,895.50

How this estimate works

Assume daily demand is independent across days and independent of supplier lead time. Allow for both sources of variation and use a normal approximation to size the stock buffer. Round safety stock and the reorder point up to whole units.

Use inventory position to trigger the reorder: units on hand plus units on order, less backorders. The chart shows on-hand units under steady consumption and instant receipt. Several purchase orders can be open at once.

EOQ balances order setup and holding costs over 365 days. The result compares the whole quantities around the continuous optimum. Review carton multiples, supplier minimums, capacity, and seasonality separately.

View the full methodology

Frequently asked questions

What exactly does the 95% service level represent?

It is the modeled probability of avoiding a stockout during a replenishment cycle. It is a cycle service level, which measures a different thing from the share of units filled immediately.

Does a shorter supplier lead time change EOQ?

It reduces lead-time demand and often the buffer. EOQ uses annual demand, ordering cost, and holding cost, so lead time has no direct effect on the economic batch size.

How should I use the reorder point if multiple POs are open?

Trigger from inventory position, which includes open incoming orders and subtracts backorders. Comparing only shelf stock can lead to duplicate orders.