Worked example · Pull replenishment
Paint-line hanger pull loop
Plan a loop of reusable hangers for a paint station with a three-quarter-day return and 30-hanger racks.
Cards = ceil(Demand × Lead time × (1 + Buffer) ÷ Bin qty)
Baseline reading
Two racks hold 60 hangers. Lead demand is 54, leaving a modeled reserve of six after rounding.
What to test
Time stripping and housekeeping tasks in the return loop. If racks sit in maintenance, treat that delay as replenishment lead time.
Worksheet inputs
Inputs
Results
- Kanban cards or containers
- 2
- Maximum loop units
- 60
- Modeled average WIP
- 33 units
- Lead-time demand
- 54 units
- Requested safety stock
- 5.4 units
- Reserve after container rounding
- 6 units
- Annual inventory turns
- 567.27×
- Average capital in loop
- $462.00
- Maximum capital in loop
- $840.00
Model notes
Lead time starts when consumption sends the signal and ends when replenished stock can be used. Keep demand days and lead-time days on the same operating calendar.
The average models a straight drawdown from full inventory to the remaining reserve during a lead-time cycle. Use actual stock history to check inventory turns.
Frequently asked questions
How should damaged hangers be represented in the paint loop?
Exclude unusable hangers from active stock and track replacements as a separate loss. Use only verified usable rack capacity as the bin quantity.
Can hanger demand be measured in painted parts instead of hangers?
Convert to hangers consumed per day using the rack loading pattern, or define both demand and container quantity in a consistently equivalent unit.