Worked example · Pull replenishment
Supplier casting supermarket buffer
Size a casting supermarket for 2.5 operating days of lead time and 100 castings per pallet.
Cards = ceil(Demand × Lead time × (1 + Buffer) ÷ Bin qty)
Baseline reading
Demand through the lead window is 800 castings. The 25% reserve brings the target to exactly ten full pallets.
What to test
Include incoming inspection release in the actual elapsed operating lead time. Recheck the math if arrivals queue for inspection during peak demand.
Worksheet inputs
Inputs
Results
- Kanban cards or containers
- 10
- Maximum loop units
- 1,000
- Modeled average WIP
- 600 units
- Lead-time demand
- 800 units
- Requested safety stock
- 200 units
- Reserve after container rounding
- 200 units
- Annual inventory turns
- 128×
- Average capital in loop
- $13,800.00
- Maximum capital in loop
- $23,000.00
Model notes
Lead time starts when consumption sends the signal and ends when replenished stock can be used. Keep demand days and lead-time days on the same operating calendar.
The average models a straight drawdown from full inventory to the remaining reserve during a lead-time cycle. Use actual stock history to check inventory turns.
Frequently asked questions
Does a 25% buffer give a particular service level for castings?
The worksheet adds 200 units to lead demand. Use observed daily consumption and lead-time scatter to estimate the resulting service level.
Can I round each supplier lead-time segment up to a day?
Sum measured compatible time segments before rounding. The model accepts fractional days and rounds only the result to a full container.