Worked example · Defects and yield
Zero-defect leak-test sample
Interpret 50,000 leak tests with zero observed failures without reporting an unbounded sigma estimate.
DPMO = Defects ÷ Opportunities × 1,000,000
Baseline reading
The sample reports 0 observed DPMO and 100% observed first-pass yield. The point transform has no finite sigma at that boundary.
What to test
Use the sample size and a suitable confidence bound for an assurance statement. Keep the confirmed measurement threshold and test sensitivity with the result.
Worksheet inputs
Inputs
Results
- Defects per million opportunities
- 0
- Normal-equivalent sigma level
- —
- Defects per unit
- 0
- Opportunity yield
- 100%
- First-pass unit yield
- 100%
- Rolled throughput yield
- —
- Total defect opportunities
- 50,000
Model notes
Measure first-pass unit yield with the number of units that failed at least once. If that tally is blank, the worksheet estimates unit yield as exp(−DPU) under a Poisson model.
The 1.5σ option adds a reporting convention to a one-sided normal equivalent. Use consistent opportunity definitions when comparing processes.
Frequently asked questions
Can a zero-failure leak run establish a literal zero leak rate?
The result establishes zero observed failures in the tested sample. A confidence bound and the detector’s sensitivity help quantify what the campaign can support.
Why is the unshifted sigma value blank in this leak example?
The inverse-normal point estimate is unbounded at zero observed opportunity defects. The worksheet displays an unavailable value with an explanation.