Drying Budget for 27% Corn at Harvest

Model a 48-foot hopper bin of 27% corn and compare the delivery shrink and drying bill against a 14.5% target.

Net dry marketable grain 49,136.1 bu
All results

Worksheet inputs

Bin dimensions
Measure the cylindrical grain column.
Use 0° for level grain. A peaked pile is often modeled at 28–30°.
Enter 1 for the standard volume estimate. Use a measured or published multiplier for incoming weight relative to the nominal crop weight.
Crop & delivery terms
Percentage of incoming weight under this model.
Per incoming bushel per percentage point removed.

Planning estimate

Net dry marketable grain
49,136.1 bu
Estimated incoming grain
58,094.2 bu
Geometric capacity (Winchester)
58,094.2 bu
Grain after water shrink
49,600.9 bu
Water shrink
8,493.3 bu
Handling shrink
464.8 bu
Combined shrink
15.42 %
Estimated incoming mass
1,475.66 t
Estimated marketable mass
1,248.12 t
Filled volume
72,295.7 ft³
Moisture removed
12.5 points
Estimated drying cost
$39,939.77
Bin section & bushel balance
Bin section & bushel balance48 ft diameterFilled bin72,295.7 ft³Marketable after shrink49,136.1 buMarketableWater shrinkHandling

Field note

A wet harvest can limit receiving throughput before volume becomes the constraint. Ask the buyer about maximum inbound moisture and coordinate dryer capacity separately.

Questions from the field

Why does this case take off more than 12.5% of bushels?

Twelve and a half points measures the change in the moisture percentage. Water shrink divides those points by the target dry-matter percentage and then handling adds a separate deduction.

Can I use this estimate to decide whether corn is safe to store?

Use extension storage guidance for moisture, temperature, aeration and storage duration. The worksheet estimates quantities and fees.