An Ideal Pass Before Turn and Refill Losses

Use a 100% efficiency boundary to compare an ideal 80-acre pass at a 20-foot swath with later field observations.

Effective field capacity 12.12 ac/h
All results

Worksheet inputs

Pass details
65–90% is a starting range for many operations. Use your field records.
Tractor & diesel

Planning estimate

Effective field capacity
12.12 ac/h
Theoretical field capacity
12.12 ac/h
Total time in field
6.6 h
Ideal pass time at full utilization
6.6 h
Time allowed for field losses
0 h
Estimated fuel burn per hour
4.88 gal/h
Estimated fuel burn per area
0.403 gal/ac
Estimated diesel for this pass
32.23 US gal
Estimated fuel cost per area
$1.45 per ac
Estimated total fuel cost
$116.04
Capacity kept & time lost
Capacity kept & time lostField capacity12.12 ac/h effective12.12 ac/h theoreticalTime in field6.6 h totalIdeal productive timeField losses

Field note

The ideal case gives a lower bound on pass time for the entered speed and width. Update the efficiency using timed work and acres completed in a real field.

Questions from the field

Why do effective and theoretical capacity match in this example?

At 100% efficiency, no capacity is discounted for overlap, stops or turns.

How can I estimate real efficiency after timing a pass?

Divide actual completed area per field hour by theoretical area per hour and express it as a percentage.