Large capstan amplification on an S-bend equivalent

Screen a 270° total bend on a 2 in. PVC route before a 180 m straight.

Inputs

Choose the raceway and size, then enter the measured bore and cable outside diameter. Open Bend and pull to enter the planned route details.

Conduit and cable bundle
mm
mm
Bend and pull
mm
°
m
N/m
μ
N
N
Cable minimum bend factors
×
×
LIVE ANATOMY

Conduit cross-section and pull profile

Conduit cross-section and pull profileCONDUIT FILL15.18%LOADED BEND200mmPULL TENSION3,889.89NPULL ROOM-1.2e+3NAREA EQUIVALENTPULL PROFILE4 cables · 15.2%Bore 51.33 mmBend 270°Out 3,889.89 NINSTALLATION LIMIT USE0%100% limit144.1% used
Installation limit exceededCheck the following limits again: pull tension.

Conduit and bends

Internal conduit area
2,069.617 mm²
Total cable area
314.159 mm²
Calculated fill
15.18 %
NEC fill limit
40 %
Minimum static bend radius
100 mm
Minimum loaded bend radius
200 mm

Pull profile

Tension exiting bend
3,501.09 N
Straight-run contribution
388.8 N
Total pull tension
3,889.89 N
Rated tension remaining
-1,189.89 N
Estimated sidewall load
8,752.726 N/m

What to check

Combining turns at one tension entry is a model. Use the actual sequence of straights and bends in the pull plan.

Open the general conduit fill & pull tension calculator

Formulas and assumptions

Conduit area and NEC fill

Fill (%) = 100 × count × (cable OD / conduit ID)²

NEC Chapter 9 Table 1 uses 53% for one cable, 31% for two and 40% for three or more when that table applies. The diagram shows equivalent area. Installation clearances and jamming depend on the actual cable geometry.

Static and loaded bends

Rstatic = 10 × OD; Rloaded = 20 × OD

These are editable planning multipliers. Compare the planned bend with the cable manufacturer’s loaded minimum and use the actual measured bore for fill.

Capstan pull model

Tout = Tin × e^(μθ) + μ × W × L

Enter the bend angle in degrees. The model uses radians, total bundle weight per length W, and a horizontal straight section after the bend. Sidewall loading at the bend exit is a simple tension/radius estimate.

EMT uses nominal planning bores. The Schedule 40 PVC presets use minimum electrical-conduit bores from the linked CANTEX drawing. HDPE uses IPS SDR 13.5 geometry before wall tolerances. Enter the actual product bore and verify the locally adopted code. The initial 600 lbf threshold is about 2,669 N. Some cable sheets specify 2,700 N separately. Enter the actual cable or pulling assembly rating and plan complex or inclined pulls section by section.

Worked examples

Open a scenario and edit any parameter.