Positive prismoidal correction in a roadway reach
Compare unequal end areas with a midsection smaller than their average.
More examplesSurvey anatomy
Parcel & roadway cross sections
Computed results
Areas agree
Boundary geometry
- Shoelace area
- 16,987.5m²
- Square feet
- 182,851.9282ft²
- Acres
- 4.1977ac
- Hectares
- 1.69875ha
- DMD area
- 16,987.5m²
- Perimeter
- 505.0025m
- Point order
- Counterclockwise
Roadway volumes
- Average end area
- 1,600m³
- Average end area
- 2,092.72099yd³
- Prismoidal volume
- 1,200m³
- Prismoidal volume
- 1,569.54074yd³
- Correction Cₚ
- 400m³
- Correction Cₚ
- 523.18025yd³
Boundary courses and DMD
| Leg | Start Nm | Start Em | ΔNm | ΔEm | DMDm | DMD × ΔNm² |
|---|---|---|---|---|---|---|
| 1 | 1,500 | 2,100 | 15 | 130 | 130 | 1,950 |
| 2 | 1,515 | 2,230 | 85 | 25 | 285 | 24,225 |
| 3 | 1,600 | 2,255 | 40 | −95 | 215 | 8,600 |
| 4 | 1,640 | 2,160 | −60 | −80 | 40 | −2,400 |
| 5 | 1,580 | 2,080 | −80 | 20 | −20 | 1,600 |
Worked check
The average of the ends is 40 m². Simpson weighting gives a 30 m² equivalent section. Multiplying both by 40 m gives a 400 m³ correction.
- Average-end-area volume (m³)
- 1,600
- Prismoidal volume (m³)
- 1,200
- Prismoidal correction (m³)
- 400
These checks describe the original example. Reset restores the original inputs.
Formulas and conventions
Compute plane-coordinate area
Signed double area = Σ(EᵢNᵢ₊₁ − Eᵢ₊₁Nᵢ)
Use three to eight distinct corners in perimeter order. The perimeter sums straight edges. The absolute half-sum is enclosed area. Positive signed area corresponds to counterclockwise order in a north-up plan.
Cross-check by DMD
DMD₁ = ΔE₁ · DMDᵢ = DMDᵢ₋₁ + ΔEᵢ₋₁ + ΔEᵢ · Area = |Σ(DMDᵢΔNᵢ)| ÷ 2
Both methods translate to a local origin before calculation. Acres use the International-foot definition; square U.S. survey feet are also reported when that working unit is selected.
Compare two roadway section volumes
AEA = L(A₁ + A₂) ÷ 2 · V = L(A₁ + 4Aₘ + A₂) ÷ 6 · Cₚ = AEA − V
Take Aₘ at the true midpoint. The prismoidal formula is exact for a prismoid and for a quadratic cross-section area profile. Compare like cut or fill areas. Positive Cₚ means average end area overstates the prismoidal volume.
More worked examples
Open a case to edit its inputs and compare the original checks.
- Rectangular parcel and constant section
Check a 60 by 40 m parcel and a constant-area roadway section.
- Triangular parcel and roadway wedge
Compute a right-triangle parcel and check a linearly changing end area.
- Concave woodlot and broad midsection
Subtract a triangular notch and check a negative prismoidal correction.
- Clockwise legacy survey-foot parcel
Check a clockwise 43,560 ftUS² enclosure and volume conversion from survey-foot sections.
- Eight corners at large grid coordinates
Check a chamfered block without losing precision to large coordinate offsets.
GeoSurveyLab · Field calculation
Positive prismoidal correction in a roadway reach
Areas agree
Field inputs
- Working unit
- Meters (m)
- Number of corners
- 5
- Boundary coordinates 1
- 1500 / 2100
- Boundary coordinates 2
- 1515 / 2230
- Boundary coordinates 3
- 1600 / 2255
- Boundary coordinates 4
- 1640 / 2160
- Boundary coordinates 5
- 1580 / 2080
- Station separation
- 40 m
- First section A₁
- 20 m²
- Midsection Aₘ
- 25 m²
- Last section A₂
- 60 m²
Boundary geometry
- Shoelace area
- 16,987.5m²
- Square feet
- 182,851.9282ft²
- Acres
- 4.1977ac
- Hectares
- 1.6988ha
- DMD area
- 16,987.5m²
- Perimeter
- 505.0025m
- Point order
- Counterclockwise
Roadway volumes
- Average end area
- 1,600m³
- Average end area
- 2,092.721yd³
- Prismoidal volume
- 1,200m³
- Prismoidal volume
- 1,569.5407yd³
- Correction Cₚ
- 400m³
- Correction Cₚ
- 523.1802yd³
Boundary courses and DMD
| Leg | Start Nm | Start Em | ΔNm | ΔEm | DMDm | DMD × ΔNm² |
|---|---|---|---|---|---|---|
| 1 | 1,500 | 2,100 | 15 | 130 | 130 | 1,950 |
| 2 | 1,515 | 2,230 | 85 | 25 | 285 | 24,225 |
| 3 | 1,600 | 2,255 | 40 | −95 | 215 | 8,600 |
| 4 | 1,640 | 2,160 | −60 | −80 | 40 | −2,400 |
| 5 | 1,580 | 2,080 | −80 | 20 | −20 | 1,600 |
For planning, training, and independent checks. Have a locally licensed Professional Land Surveyor (PLS) verify legal boundaries and survey control. Have a licensed Professional Engineer (PE) verify engineering layout and design where required.