Rising crest without a high point inside
Distinguish a crest in grade change from a crest with an interior summit.
More examplesSurvey anatomy
Profile & sight-distance check
Computed results
Meets geometry
Tangent and curve controls
- PVC
- 0+750.000m
- PVC elevation
- 74m
- PVI
- 0+900.000m
- PVI tangent elevation
- 80m
- PVT
- 1+050.000m
- PVT elevation
- 81.5m
- Grade difference A
- −3%
- K rate
- 100m/%
- Interior turning point
- None
Stopping sight distance check
- Required sight distance S
- 100m
- Geometric minimum L
- 0m
- Geometric minimum K
- 0m/%
- Long-curve K at S
- 15.20103m/%
- Sizing branch
- S > L
Profile elevations and grades
| Point | Stationm | Offset from PVCm | Elevationm | Grade% |
|---|---|---|---|---|
| PVC | 0+750.000 | 0 | 74 | 4 |
| Stake | 0+800.000 | 50 | 75.875 | 3.5 |
| Stake | 0+850.000 | 100 | 77.5 | 3 |
| Stake | 0+900.000 | 150 | 78.875 | 2.5 |
| Stake | 0+950.000 | 200 | 80 | 2 |
| Stake | 1+000.000 | 250 | 80.875 | 1.5 |
| PVT | 1+050.000 | 300 | 81.5 | 1 |
Worked check
The grade is always positive and decreases from 4% to 1%. The curve is crest-shaped with no zero-grade point between PVC and PVT.
- Profile type
- Crest
- Interior turning point
- Undefined
- PVC elevation (m)
- 74
- PVT elevation (m)
- 81.5
These checks describe the original example. Reset restores the original inputs.
Formulas and conventions
Build the symmetric profile
A = g₂ − g₁ · z(x) = zPVC + g₁x ÷ 100 + Ax² ÷ (200L)
PVC and PVT are L/2 either side of the tangent intersection PVI. Grades are entered in percent. When grades have opposite signs, x = −g₁L/A is the interior turning point and its slope is exactly zero.
Join unequal tangents
gⱼ = (L₁g₁ + L₂g₂) ÷ L · zⱼ = zPVI + A L₁ L₂ ÷ (200L)
L₁ is PVC to PVI and L₂ is PVI to PVT. Each parabola integrates a linear grade between the endpoint and common join grade. Find the zero grade on the piece where the signs change. The local K values are L₁/|gⱼ − g₁| and L₂/|g₂ − gⱼ|.
Calculate the curvature rate
K = L ÷ |A|
K is length per percentage point of grade change. Equal grades form a straight tangent and have no finite K. Station labels use 100-foot stations or kilometer plus meters, depending on the working unit.
Compare the SSD geometry
Lmin = |A| S² ÷ C when Lmin ≥ S · otherwise max(0, 2S − C ÷ |A|)
For a crest, C = 200(√h₁ + √h₂)², with eye height 3.5 ft and object height 2 ft. For a sag, C = 200(h + S tan 1°), with headlight height 2 ft. The two minimum-length branches apply to equal tangents. Unequal tangents use a sufficient screen: both local K values must meet S²/C. If either is tighter, check the complete sight line. Use the adopted agency criteria and drainage controls.
More worked examples
Open a case to edit its inputs and compare the original checks.
- Symmetric metric crest high point
Solve a symmetric 2% to −2% crest and check the high point at midcurve.
- Symmetric −3% to +3% sag
Find the low point and compare its curvature rate with a required sight distance.
- Short-curve stopping sight distance
Apply the short-curve branch when the required sight distance exceeds the curve length.
- Equal grades give a straight tangent
Check elevation stationing when both grades are the same.
- Asymmetric sag in U.S. survey feet
Locate the low point of a −4% to +2% sag with unequal tangent lengths on an older alignment.
GeoSurveyLab · Field calculation
Rising crest without a high point inside
Meets geometry
Field inputs
- Working unit
- Meters (m)
- Tangent lengths
- Equal tangent lengths
- Entering grade g₁
- 4 %
- Exiting grade g₂
- 1 %
- PVI station
- 0+900 m
- PVI elevation
- 80 m
- Curve length
- 300 m
- Stake interval
- 50 m
- Required sight distance
- 100 m
Tangent and curve controls
- PVC
- 0+750.000m
- PVC elevation
- 74m
- PVI
- 0+900.000m
- PVI tangent elevation
- 80m
- PVT
- 1+050.000m
- PVT elevation
- 81.5m
- Grade difference A
- −3%
- K rate
- 100m/%
- Interior turning point
- None
Stopping sight distance check
- Required sight distance S
- 100m
- Geometric minimum L
- 0m
- Geometric minimum K
- 0m/%
- Long-curve K at S
- 15.201m/%
- Sizing branch
- S > L
Profile elevations and grades
| Point | Stationm | Offset from PVCm | Elevationm | Grade% |
|---|---|---|---|---|
| PVC | 0+750.000 | 0 | 74 | 4 |
| Stake | 0+800.000 | 50 | 75.875 | 3.5 |
| Stake | 0+850.000 | 100 | 77.5 | 3 |
| Stake | 0+900.000 | 150 | 78.875 | 2.5 |
| Stake | 0+950.000 | 200 | 80 | 2 |
| Stake | 1+000.000 | 250 | 80.875 | 1.5 |
| PVT | 1+050.000 | 300 | 81.5 | 1 |
For planning, training, and independent checks. Have a locally licensed Professional Land Surveyor (PLS) verify legal boundaries and survey control. Have a licensed Professional Engineer (PE) verify engineering layout and design where required.