Worked example
Time to 95% consolidation
A staging study checks the estimated time to reach 95% primary consolidation for a thick layer.
Results
Edit inputs ↓- Settlement
- 238.22 mm
- OCR
- 1.33
- Time to 50%
- 318.7 days
- Time to 90%
- 1,373.9 days
- Compression
- Time response
- Target
Loading crosses preconsolidation pressure. Both compression slopes contribute.
Calculation details
| Stress path | OC → NC |
|---|---|
| Final effective stress | 155 kPa |
| Final void ratio | 1.147 |
| Recompression settlement | 22.29 mm |
| Virgin compression settlement | 215.93 mm |
| Longest drainage path Hdr | 3.6 m |
| Target time factor Tv | 1.129 |
| Time to target | 1,828.99 days |
| Settlement at target | 226.31 mm |
GeotechSoilLab · Screening sheet · Metric SI
Time to 95% consolidation
| Layer thickness H₀ | 7.2 m |
|---|---|
| Initial void ratio e₀ | 1.22 |
| Initial stress σ′₀ | 72 kPa |
| Preconsolidation σ′p | 96 kPa |
| Added stress Δσ′ | 83 kPa |
| Compression index Cc | 0.32 |
| Recompression Cr | 0.055 |
| Drainage faces | Double |
| Consolidation rate cv | 0.008 m²/day |
| Target consolidation U | 95 % |
| Settlement | 238.22 mm |
|---|---|
| OCR | 1.33 |
| Time to 50% | 318.7 days |
| Time to 90% | 1,373.9 days |
| Stress path | OC → NC |
| Final effective stress | 155 kPa |
| Final void ratio | 1.147 |
| Recompression settlement | 22.29 mm |
| Virgin compression settlement | 215.93 mm |
| Longest drainage path Hdr | 3.6 m |
| Target time factor Tv | 1.129 |
| Time to target | 1,828.99 days |
| Settlement at target | 226.31 mm |
Engineering screening estimates. Use site-specific boring logs, appropriate test data and review by a licensed geotechnical PE before design or construction.
Engineering screening estimates. Use site-specific boring logs, appropriate test data and review by a licensed geotechnical PE before design or construction.
Worked result
Late-time pore-pressure dissipation slows progress. The time from 90% to 95% is substantial.
- Add 83 kPa to 72 kPa to get 155 kPa. The preconsolidation stress is 96 kPa.
- Add 22.286 mm of recompression and 215.933 mm of virgin compression to get 238.219 mm.
- Use Tv = 1.129 and Hdr = 3.6 m in TvHdr²/cv. This gives 1,829 days to 95% consolidation.
Settlement238.22 mmOCR1.33Time to 50%318.7 daysTime to 90%1,373.9 days
Original case inputs
| Layer thickness H₀ | 7.2 m |
|---|---|
| Initial void ratio e₀ | 1.22 |
| Initial stress σ′₀ | 72 kPa |
| Preconsolidation σ′p | 96 kPa |
| Added stress Δσ′ | 83 kPa |
| Compression index Cc | 0.32 |
| Recompression Cr | 0.055 |
| Drainage faces | Double |
| Consolidation rate cv | 0.008 m²/day |
| Target consolidation U | 95 % |
Method & assumptions
- OCR = σ′p / σ′₀. Settlement is H₀/(1 + e₀) times the decrease in void ratio. Use Cr log₁₀(σ′/σ′₀) up to σ′p and Cc log₁₀(σ′/σ′p) beyond it.
- For normally consolidated clay, σ′p equals σ′₀ and the full stress increment follows Cc. Overconsolidated clay uses only Cr when final stress stays below or at σ′p.
- t = Tv Hdr² / cv. Hdr is H₀ for single drainage or H₀/2 for double drainage. Tv is found from Terzaghi’s average consolidation series and its short-time limit.
- Use a representative initial stress and added stress at the layer midpoint. The method assumes one homogeneous saturated layer, one-dimensional strain, sudden loading and constant cv. Compute separate layers when properties vary.
More worked examples
- Normally consolidated clay under fillAn embankment loads a normally consolidated clay layer bounded by permeable sand.
- Overconsolidated clay below yieldA modest foundation pressure increment leaves final stress below the soil’s prior maximum.
- Clay compressed past preconsolidationA heavy fill increment pushes an overconsolidated clay through its yield stress.
- Clay with single-sided drainageA clay layer is drained at its top and underlain by nearly impermeable material.
- Loading that reaches preconsolidation stressA staged load raises the effective stress exactly to the estimated preconsolidation stress.