When a sand delivery hits payload before volume

A contractor needs 4 in of loose sand over a 42 × 18 ft work area. Check a 10 yd³ truck with a 7 US ton payload at 100 lb/ft³.

Project inputs

Footprint and depth
ft
ft
in
Material and order
lb/ft³
Preset densities are estimates. Use the supplier’s loose bulk density when known.
%
The fraction of loose volume lost as material settles or compacts.
%
ft³/bag
yd³
US tons

Material & layout estimate

Bulk volume to order

9.33 yd³
Order volume in alternate units
7.14 m³
Estimated loose weight
12.6 US tons
Metric equivalent weight
11.43 t
Whole bags
504
Estimated truckloads
2
Coverage area
756 ft²
Finished volume
9.33 yd³
Loose volume before allowance
9.33 yd³

Payload limits the load estimate. Confirm both limits and loose density with the supplier.

Material depth & delivery loads Schematic
Material depth & delivery loadsBulk volume to order: 9.33 yd³. Order volume in alternate units: 7.14 m³. Estimated loose weight: 12.6 US tons. Metric equivalent weight: 11.43 t FOOTPRINT756 ft²SECTION4 in finished depthORDER & LOADS9.33 yd³12.6 US tons loose weightBed volumePayload2 truckloads

Starting estimate

The bed can hold the calculated volume in one trip, but the load weighs more than the entered payload. The payload estimate requires two trips.

Bulk volume to order
9.33 yd³
Estimated loose weight
12.6 US tons
Estimated truckloads
2

How the estimate works

  1. Find the footprint area and multiply it by the finished material depth. For irregular yard sections, add measured areas and enter the total as Known area.
  2. Divide installed volume by the fraction left after compaction. Multiply that loose volume by one plus the order allowance.
  3. Multiply the order volume by loose density for weight. Round up bags and check both volume and payload when counting delivery loads.

Questions and answers

Why does the 9⅓ yd³ sand order need two truckloads with a 10 yd³ bed?

It weighs an estimated 12.6 US tons. The stated 7 US ton payload is the limiting factor, so two trips are needed.

What if wet sand arrives heavier than the 100 lb/ft³ assumption?

Enter the current quoted density and check the supplier’s legal payload for the vehicle on your route. The planning estimate changes with density.