Starting estimate
The nominal 864-paver field needs 968 pieces with the 12% cut allowance. Joint sand is a separate five-bag estimate at the entered coverage.
- Pavers to buy
- 968
- Polymeric sand bags
- 5
How the estimate works
- Multiply patio length by width. Divide the area by a laid paver module’s footprint, including the designed joint if the supplied dimensions exclude it.
- Apply the cutting allowance and buy whole pavers. Multiply area by layer depth separately for installed aggregate and bedding sand.
- Divide patio area by the joint-sand bag coverage. Subtract fixed edges from the total perimeter, then divide the remaining length by the spike spacing.
Questions and answers
What allowance does the herringbone dining patio start with?
The herringbone preset adds 12% to the nominal field. Adjust this input after sketching the border and checking whether you can reuse edge cuts.
Does a picture-frame paver border come out of the 968 count?
The estimate assumes one module across the entire footprint. Measure the border and field separately when they use different pavers or joint layouts.