Worked example

Running bond takeoff for a 12 × 10 ft patio

Count 4 × 8 in modules for a 120 ft² seating patio with a 4 in compacted base, 1 in bedding, and edging on all sides.

Project inputs

Patio footprint
ft
ft
in
in
%
Layers and edges
in
A 4–6 in planning range suits many simple pedestrian patios. Verify the assembly for your site.
in
ft²/bag
Use bag coverage for the actual joint width and depth.
ft
in

Material & layout estimate

Pavers to buy

573
Compacted base volume
1.48 yd³
Bedding sand volume
0.37 yd³
Polymeric sand bags
3
Edge restraint length
44 ft
Spikes at entered spacing
44
Patio area
120 ft²
Area per paver module
0.2222 ft²

Layer volumes are installed quantities. Ask your supplier how much loose aggregate is needed to reach the specified compacted depth.

Paver layout & base layers Schematic
Paver layout & base layersPavers to buy: 573. Compacted base volume: 1.48 yd³. Bedding sand volume: 0.37 yd³. Polymeric sand bags: 3 PATTERN / PLANRunning bond12 ft × 10 ftPATIO SECTION573 paversPaver course1 in bedding sand4 in compacted base

Starting estimate

The face area fits 540 modules before cuts. The 6% running bond allowance brings the purchase count to 573 pavers.

Pavers to buy
573
Compacted base volume
1.48 yd³
Edge restraint length
44 ft

How the estimate works

  1. Multiply patio length by width. Divide the area by a laid paver module’s footprint, including the designed joint if the supplied dimensions exclude it.
  2. Apply the cutting allowance and buy whole pavers. Multiply area by layer depth separately for installed aggregate and bedding sand.
  3. Divide patio area by the joint-sand bag coverage. Subtract fixed edges from the total perimeter, then divide the remaining length by the spike spacing.

Questions and answers

Where does the 44 ft edging estimate come from on a 12 × 10 patio?

Two 12 ft sides plus two 10 ft ends make 44 ft. Enter any edge already restrained by the approved design to remove it from the purchase count.

How much compacted aggregate is under this 120 ft² running bond patio?

A 4 in layer uses 40 ft³, or about 1.48 yd³ compacted. Ask the quarry for the delivered amount yielding that compacted volume.