Opposed parking lot poles

Use two fixtures across a vehicle aisle at each longitudinal station and check equivalent power per kilometer.

Road and mounting
ft
ft
ft
×
Luminaire and target
lm
fc
W
Pole pitch
160.07ft
Pitch / height
4.44×
Pole density
66poles/mi
Linear power
5.94kW/km

Pole elevation and layout plan

Edit inputs ↓
Pole elevation and layout planCURB SECTIONROADWAY PLANH 36.09 ftOppositeArm 5.91 ftS 160.07 ftMaintained target1.3 fc
Pitch is measured along one side. A staggered arrangement offsets the opposite row by half the pitch.

RP-8 layout screen

Review needed
OutsideThresholdWithin
  • Same-side pitch / height4.44 / ≤ 4 × outside screen

Comparison uses the entered pitch criterion. Use the relevant RP-8 limits in a point-by-point pavement grid.

Additional readings
Luminaires per repeat2
Combined light loss factor0.765
Maintained delivered flux per repeat12,295.08lm
Area-normalized connected power0.031W/ft²
Optical overhang5.91ft
Distance to next pole station160.07ft
Pitch limit from height criterion144.36ft

Worked calculation

US customary results for the original preset.

  1. Apply utilization and loss factors over 2 poles per repeat to get 12295.08 lm maintained.
  2. Divide by the road width and target illuminance to get 160.07 ft same-side pitch. The pitch-to-height ratio is 4.44.
  3. Scale the repeat to 66 poles/mi and 5.94 kW/km of linear connected power.

Calculation method

Select a maintained illuminance target for the road or parking class. Apply the street-side utilization and light loss to the flux in one repeating roadway cell.

Maintained lumens through one cell
Φcell = Φ × CU × LLD × LDD × fixtures per repeat
Same-side pole pitch
S = Φcell/(Eavg × roadway width)
Pole density and power
Poles/km = 1000 × fixtures per repeat/S · kW/km = poles/km × W/1000

The supplied spacing / height limit is a project heuristic. Verify RP-8 pavement uniformity, glare, luminance, and classification using grid photometry.

Sources and assumptions ↗