The two covers and runner project 159 cm². The required force exceeds the entered press limit.
A_proj = N × A_part + A_runner. F_required (kN) = 0.1 × A_proj (cm²) × P_cavity (MPa) × SF.
Use the silhouette in the clamp direction, including the projected feed system. Enter mean cavity pressure at the limiting fill or packing condition. The pressure tiers are starting estimates. Use a measured or simulated cavity pressure for press selection when available. The utilization boundary compares the calculated force with the entered rating.