Required reactive power
Q_C = P · [tan(acos(PF₁)) − tan(acos(PF₂))]
Active kW stays constant. Use lagging power factors with the target at least as high as the original. Upstream apparent power falls from P/PF₁ to P/PF₂.
A 415 V process area wants extra transformer capacity even though its current tariff has no PF penalty.
Compute kVAR for 180 kW from 0.77 to 0.94. Both penalty inputs are zero, so the economics section has zero savings and no finite payback.
Values in this solution use the original example inputs.
Q_C = P · [tan(acos(PF₁)) − tan(acos(PF₂))]
Active kW stays constant. Use lagging power factors with the target at least as high as the original. Upstream apparent power falls from P/PF₁ to P/PF₂.
C_phase = Q_C · 10⁹ / (3 · 2πf · V_C²) [µF]
Use V_C = V_LL for Delta and V_LL/√3 for Wye. Wye requires three times the capacitance per phase at equal kVAR, line voltage, and frequency.
h₀ ≈ √(1000 · MVA_sc / Q_C); f₀ = f · h₀
Screen an undetuned bank on a predominantly inductive source. An alert within 0.5 of an odd order from 3 to 13 flags a case for spectrum and switching-step review. Check other orders and actual bus configurations.
I = 1000 · S / (√3 · V_LL), payback = installed cost / monthly penalty reduction
Enter the tariff penalty for each condition. A positive reduction with a nonzero bank is required for a simple payback. The currency selector changes units only.
Balanced sinusoidal load. Compare manufacturer voltage, step size, inrush and switching duties. Review harmonics, resonance, and light-load overcompensation before choosing a bank.