Efficiency maximum at half load

A 500 kVA transformer has 1,000 W core loss and 4,000 W load loss at nameplate current.

Inputs

Nameplate & source
Use 0 for infinite bus. Enter utility fault MVA at the transformer primary.
Enter the nameplate or test ratio for peak fault estimates. Use 0 if unknown.
Use 0 to assume the utility impedance has the same angle as the transformer.
Losses & loading
Use 0 to omit minimum kVA sizing.

Transformer efficiency and fault duty

60 Hz · US customaryEdit inputs
Transformer efficiency and fault duty at 60 Hz SECONDARY FLA601.41ABOLTED FAULT10.46kAEFFICIENCY99.165%MINIMUM KVA388.16kVAEfficiency vs. loading100% efficiency95%6.3% load100% loadSecondary fault duty13.8 kV480 VInfinite bus10.46 kAFinite-bus input omittedNameplate loading50% load100% rated

Detailed results
Primary full-load current
20.92 A
Secondary full-load current
601.41 A
Infinite-bus symmetrical fault
10.46 kA
Finite-bus symmetrical fault
Unavailable
Infinite-bus L–L fault on three-phase supply
9.06 kA
Finite-bus L–L fault on three-phase supply
Unavailable
Infinite-bus asymmetrical peak
Unavailable
Finite-bus asymmetrical peak
Unavailable
Operating efficiency
99.165%
Mathematical peak efficiency load
50%
Peak efficiency through rated load
99.165%
Operating output power
237.5 kW
Operating load loss
1,000 W
Operating total loss
2,000 W
Minimum design capacity
388.16 kVA
Nameplate above minimum
111.84 kVA

Worked calculation

The square root of 1,000/4,000 gives 0.50 pu peak load. At that point the winding loss is 0.50²·4,000 = 1,000 W and total modeled losses are 2,000 W.

Mathematical peak efficiency load
50%
Operating total loss
2,000 W
Operating efficiency
99.165%

Values in this solution use the original example inputs.

Formulas & assumptions

Rated current and capacity

I_FLA = 1000 · kVA / (g · V), kVA_min = design kW / (PF · target load fraction)

Use g = √3 and line-to-line voltage for three-phase, or g = 1 and applied winding voltage for single-phase. Select a nameplate rating and check the reserve.

Terminal bolted fault

I_sc = I_FLA / |Z_tx + Z_src|; Z_src,pu = rated kVA / utility fault kVA

The infinite-bus case sets Z_src to zero. Enter X/R to add resistance and reactance on the same base. Without X/R, the impedance magnitudes are added assuming equal angles. For a three-phase supply with equal positive and negative sequence impedance, the L–L fault is √3/2 times the three-phase fault.

Asymmetrical peak screen

i_peak ≈ √2 · I_sc · [1.02 + 0.98 · exp(−3R/X)]

Uses the combined radial terminal impedance and nominal prefault voltage. Peak values refer to the symmetrical fault results above. They omit standard voltage and equipment correction factors and are for screening.

Losses and efficiency

η = P_out / (P_out + P₀ + x² · P_cu), x_peak = √(P₀ / P_cu)

x is load fraction relative to nameplate kVA and P_out = x · rated kVA · PF. Use consistent watts. Peak efficiency occurs when modeled load loss equals core loss.

Nominal RMS voltages, symmetric bolted fault at secondary terminals, and losses at a fixed reference temperature. Check source X/R, service voltage, impedance tolerance, downstream impedance, and contributions from motors and generators in a fault study.

Engineering references

More worked examples