WeldMetalLab

Consumable estimating

Weld Filler Metal Weight & Cost

Estimate weld metal, filler purchases, arc-on time and labor from a fillet or a prepared groove.

Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.

Inputs

Joint geometry
mm
m
Use length per side for a double fillet.
%
Process & costing
kg/m³
kg/h
%
USD/kg
USD/h
USD

Live weld sheet

Updated from inputs
Weld cross-sectionFilled cross-section 39.6 mm². Filler to purchase 4.549 kg. Arc-on time 69.94 min. Filler and labor cost 235.61 USD WELD AREA39.6mm²PURCHASED4.549kgARC TIME69.94minTOTAL COST235.61USD WELD CROSS-SECTION Leg 6 mmSeam 12 mDouble fillet COST ALLOWANCEPASS
Pass · within screen

Cost allowance · Filler + labor vs 250 USD.

Result details

Filled cross-section39.6 mm²
Filler to purchase4.549 kg
Arc-on time69.94 min
Filler and labor cost235.61 USD
Base weld section36 mm²
Deposited volume475.2 cm³
Theoretical deposited mass3.73 kg
Consumable loss0.819 kg
Deposition efficiency82 %
Net deposition rate3.2 kg/h
Gross consumption rate3.9 kg/h
Paid shop time199.84 min
Filler cost29.11 USD
Labor cost206.5 USD
Budget margin14.39 USD

Calculation method

A = A₀(1 + r) · m = ρAL · mᵦ = m / ηd

An equal-leg fillet starts at w²/2 per side. A symmetric single V has section g·t + (t − f)²·tan(α/2). A balanced double V halves the bevel term at the same total root face. For a single bevel, use g·t + ½(t − f)²·tan(β). Reinforcement adds the entered percentage to the full base section.

The model assumes uniform density and a constant net deposition rate. Divide deposited mass by the process yield to estimate purchases. Divide arc-on time by the arc-on factor to obtain paid shop time. The cost screen compares filler plus labor against your allowance. Add gas, flux, setup or handling to your estimate separately.