WeldMetalLab

Consumable estimating

Short SMAW repair with low arc-on factor

A short repair requires repeated repositioning and electrode changes. Use a conservative 12% arc-on factor for the quote.

Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.

Inputs

Joint geometry
in
ft
Use length per side for a double fillet.
%
Process & costing
lb/in³
lb/h
%
USD/lb
USD/h
USD

Live weld sheet

Updated from inputs
Weld cross-sectionFilled cross-section 0.038 in². Filler to purchase 0.491 lb. Arc-on time 13.36 min. Filler and labor cost 172.12 USD WELD AREA0.038in²PURCHASED0.491lbARC TIME13.36minTOTAL COST172.12USD WELD CROSS-SECTION Leg 0.25 inSeam 2.5 ftSingle fillet COST ALLOWANCEFAIL
Outside screen

Cost allowance · Filler + labor vs 12 USD.

Result details

Filled cross-section0.038 in²
Filler to purchase0.491 lb
Arc-on time13.36 min
Filler and labor cost172.12 USD
Base weld section0.031 in²
Deposited volume1.13 in³
Theoretical deposited mass0.319 lb
Consumable loss0.172 lb
Deposition efficiency65 %
Net deposition rate1.43 lb/h
Gross consumption rate2.2 lb/h
Paid shop time111.32 min
Filler cost1.42 USD
Labor cost170.69 USD
Budget margin-160.12 USD

Worked example

Starting inputs

Weld profile
Single fillet
Equal leg size
0.25 in
Seam length
2.5 ft
Extra weld area
20 %
Welding process
SMAW
Net deposition rate
1.433005 lb/h
Arc-on factor
12 %

Baseline results

Filled cross-section
0.038 in²
Filler to purchase
0.491 lb
Arc-on time
13.36 min
Filler and labor cost
172.12 USD

A filled section of 0.038 in² over 2.5 ft deposits 0.319 lb. At 65 % process yield, allow 0.491 lb of consumables.

Try it. When the seam is short, paid time can dominate the estimate even when the electrode mass is small.

Calculation method

A = A₀(1 + r) · m = ρAL · mᵦ = m / ηd

An equal-leg fillet starts at w²/2 per side. A symmetric single V has section g·t + (t − f)²·tan(α/2). A balanced double V halves the bevel term at the same total root face. For a single bevel, use g·t + ½(t − f)²·tan(β). Reinforcement adds the entered percentage to the full base section.

The model assumes uniform density and a constant net deposition rate. Divide deposited mass by the process yield to estimate purchases. Divide arc-on time by the arc-on factor to obtain paid shop time. The cost screen compares filler plus labor against your allowance. Add gas, flux, setup or handling to your estimate separately.