Single V SMAW plate splice

A 3/4 in plate splice is prepared with a 60° V and a 1/8 in root gap. Estimate electrode purchases for a 12 ft seam.

Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.

Inputs

Joint geometry
in
in
in
°
Included angle for V grooves. Use the angle on the prepared edge for a single bevel.
ft
Use length per side for a double fillet.
%
Process & costing
lb/in³
lb/h
%
USD/lb
USD/h
USD

Live weld sheet

Updated from inputs
Weld cross-sectionFilled cross-section 0.403 in². Filler to purchase 25.339 lb. Arc-on time 344.8 min. Filler and labor cost 1,261.21 USD WELD AREA0.403in²PURCHASED25.339lbARC TIME344.8minTOTAL COST1,261.21USD WELD CROSS-SECTION Plate 0.75 inGap 0.125 inSingle V COST ALLOWANCEFAIL
Outside screen

Cost allowance · Filler + labor vs 180 USD.

Result details

Filled cross-section0.403 in²
Filler to purchase25.339 lb
Arc-on time344.8 min
Filler and labor cost1,261.21 USD
Base weld section0.367 in²
Deposited volume58.08 in³
Theoretical deposited mass16.47 lb
Consumable loss8.869 lb
Deposition efficiency65 %
Net deposition rate2.87 lb/h
Gross consumption rate4.41 lb/h
Paid shop time1,149.34 min
Filler cost73.56 USD
Labor cost1,187.66 USD
Budget margin-1,081.21 USD

Worked example

Starting inputs

Weld profile
Single V groove
Plate thickness
0.75 in
Root gap
0.125 in
Total root face
0.0625 in
Groove angle
60 °
Seam length
12 ft
Extra weld area
10 %

Baseline results

Filled cross-section
0.403 in²
Filler to purchase
25.339 lb
Arc-on time
344.8 min
Filler and labor cost
1,261.21 USD

A filled section of 0.403 in² over 12 ft deposits 16.47 lb. At 65 % process yield, allow 25.339 lb of consumables.

Try it. Compare deposited mass with consumed electrodes. The 65% yield accounts for the planning allowance for stub and process losses.

Calculation method

A = A₀(1 + r) · m = ρAL · mᵦ = m / ηd

An equal-leg fillet starts at w²/2 per side. A symmetric single V has section g·t + (t − f)²·tan(α/2). A balanced double V halves the bevel term at the same total root face. For a single bevel, use g·t + ½(t − f)²·tan(β). Reinforcement adds the entered percentage to the full base section.

The model assumes uniform density and a constant net deposition rate. Divide deposited mass by the process yield to estimate purchases. Divide arc-on time by the arc-on factor to obtain paid shop time. The cost screen compares filler plus labor against your allowance. Add gas, flux, setup or handling to your estimate separately.

References

More worked examples