Consumable estimating
Single V SMAW plate splice
A 3/4 in plate splice is prepared with a 60° V and a 1/8 in root gap. Estimate electrode purchases for a 12 ft seam.
Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.
Inputs
Live weld sheet
Updated from inputsCost allowance · Filler + labor vs 180 USD.
Result details
| Filled cross-section | 0.403 in² |
|---|---|
| Filler to purchase | 25.339 lb |
| Arc-on time | 344.8 min |
| Filler and labor cost | 1,261.21 USD |
| Base weld section | 0.367 in² |
| Deposited volume | 58.08 in³ |
| Theoretical deposited mass | 16.47 lb |
| Consumable loss | 8.869 lb |
| Deposition efficiency | 65 % |
| Net deposition rate | 2.87 lb/h |
| Gross consumption rate | 4.41 lb/h |
| Paid shop time | 1,149.34 min |
| Filler cost | 73.56 USD |
| Labor cost | 1,187.66 USD |
| Budget margin | -1,081.21 USD |
Worked example
Starting inputs
- Weld profile
- Single V groove
- Plate thickness
- 0.75 in
- Root gap
- 0.125 in
- Total root face
- 0.0625 in
- Groove angle
- 60 °
- Seam length
- 12 ft
- Extra weld area
- 10 %
Baseline results
- Filled cross-section
- 0.403 in²
- Filler to purchase
- 25.339 lb
- Arc-on time
- 344.8 min
- Filler and labor cost
- 1,261.21 USD
A filled section of 0.403 in² over 12 ft deposits 16.47 lb. At 65 % process yield, allow 25.339 lb of consumables.
Try it. Compare deposited mass with consumed electrodes. The 65% yield accounts for the planning allowance for stub and process losses.
Calculation method
A = A₀(1 + r) · m = ρAL · mᵦ = m / ηd
An equal-leg fillet starts at w²/2 per side. A symmetric single V has section g·t + (t − f)²·tan(α/2). A balanced double V halves the bevel term at the same total root face. For a single bevel, use g·t + ½(t − f)²·tan(β). Reinforcement adds the entered percentage to the full base section.
The model assumes uniform density and a constant net deposition rate. Divide deposited mass by the process yield to estimate purchases. Divide arc-on time by the arc-on factor to obtain paid shop time. The cost screen compares filler plus labor against your allowance. Add gas, flux, setup or handling to your estimate separately.