Long-haul interstate segment

Size a truck fleet for two hours of round-trip haul, queue and load time.

Design readout

Gross HMA
1,569.7
US tons
Tack to spray
1,432.8
US gal
Paver demand
336.4
US tons/h
Haul trucks
27

Tack and paver plan view

Tack and paver plan viewPAVING PLANTACK COVERAGECOMPACTEDTACKMAT LENGTH7,200 ftMAT WIDTH12 ftSPRAY VOLUME1.4e3 US gal
The sprayed footprint covers the entered mat area. Fleet sizing uses one complete round-trip cycle.

Plant below paver demand

Marker shows plant output relative to paver demand. The tack check uses the selected surface band.

Calculation ledger
Net compacted HMA
1,495 US tons
Compacted mix density
151.01 lb/ft³
Tack coverage area
9,600 yd²
Route length
1.364 mi
Residual binder volume
480 US gal
Undiluted emulsion volume
716.4 US gal
Diluted distributor bar rate
0.149 gal/yd²
Plant/paver limited throughput
325 US tons/h
Fleet at feasible throughput
26
Gross mix supply time
4.83 h
Reference residual tack minimum
0.04 gal/yd²
Reference residual tack maximum
0.07 gal/yd²

Inputs

Changes update results

Compacted mat
ft
ft
in
%
Tack coat
gal/yd²
%
%
Production and haul
US tons/h
ft/min
US tons
min

Work through this example

  1. Multiply mat volume by compacted density and add the purchase allowance.
  2. Convert the required residual binder into supplied emulsion and diluted spray volumes.
  3. Convert paver travel into mix demand and round truck fleet sizes up.

Shorten the round trip and observe the discrete changes in truck count.

Check tack rate and dilution against the contract and emulsion supplier. The steady-state haul model assumes uniform payload and cycle time.

Read the equations and sources