Asphalt lift over PCC

Check quantities and tack for an asphalt lift placed over a concrete pavement.

Design readout

Gross HMA
449.5
US tons
Tack to spray
365.7
US gal
Paver demand
305.8
US tons/h
Haul trucks
18

Tack and paver plan view

Tack and paver plan viewPAVING PLANTACK COVERAGECOMPACTEDTACKMAT LENGTH1,960 ftMAT WIDTH15 ftSPRAY VOLUME365.7 US gal
The sprayed footprint covers the entered mat area. Fleet sizing uses one complete round-trip cycle.

Plant below paver demand

Marker shows plant output relative to paver demand. The tack check uses the selected surface band.

Calculation ledger
Net compacted HMA
416.2 US tons
Compacted mix density
151.01 lb/ft³
Tack coverage area
3,266.7 yd²
Route length
0.371 mi
Residual binder volume
147 US gal
Undiluted emulsion volume
219.4 US gal
Diluted distributor bar rate
0.112 gal/yd²
Plant/paver limited throughput
280 US tons/h
Fleet at feasible throughput
16
Gross mix supply time
1.61 h
Reference residual tack minimum
0.03 gal/yd²
Reference residual tack maximum
0.05 gal/yd²

Inputs

Changes update results

Compacted mat
ft
ft
in
%
Tack coat
gal/yd²
%
%
Production and haul
US tons/h
ft/min
US tons
min

Work through this example

  1. Multiply mat volume by compacted density and add the purchase allowance.
  2. Convert the required residual binder into supplied emulsion and diluted spray volumes.
  3. Convert paver travel into mix demand and round truck fleet sizes up.

Compare net compacted asphalt with the order quantity after the 8% purchase allowance.

Check tack rate and dilution against the contract and emulsion supplier. The steady-state haul model assumes uniform payload and cycle time.

Read the equations and sources