Plant-limited paving shift

Evaluate a paver that can place more material per hour than the plant can supply.

Design readout

Gross HMA
941.8
US tons
Tack to spray
788.1
US gal
Paver demand
713.5
US tons/h
Haul trucks
45

Tack and paver plan view

Tack and paver plan viewPAVING PLANTACK COVERAGECOMPACTEDTACKMAT LENGTH2,640 ftMAT WIDTH18 ftSPRAY VOLUME788.1 US gal
The sprayed footprint covers the entered mat area. Fleet sizing uses one complete round-trip cycle.

Plant below paver demand

Marker shows plant output relative to paver demand. The tack check uses the selected surface band.

Calculation ledger
Net compacted HMA
897 US tons
Compacted mix density
151.01 lb/ft³
Tack coverage area
5,280 yd²
Route length
0.5 mi
Residual binder volume
264 US gal
Undiluted emulsion volume
394 US gal
Diluted distributor bar rate
0.149 gal/yd²
Plant/paver limited throughput
190 US tons/h
Fleet at feasible throughput
12
Gross mix supply time
4.96 h
Reference residual tack minimum
0.04 gal/yd²
Reference residual tack maximum
0.07 gal/yd²

Inputs

Changes update results

Compacted mat
ft
ft
in
%
Tack coat
gal/yd²
%
%
Production and haul
US tons/h
ft/min
US tons
min

Work through this example

  1. Multiply mat volume by compacted density and add the purchase allowance.
  2. Convert the required residual binder into supplied emulsion and diluted spray volumes.
  3. Convert paver travel into mix demand and round truck fleet sizes up.

The fleet for theoretical paver demand and feasible dispatch fleet differ in the ledger.

Check tack rate and dilution against the contract and emulsion supplier. The steady-state haul model assumes uniform payload and cycle time.

Read the equations and sources