Worked example

Rebar for a 24 ft garage mat at 12 in O.C.

A garage slab has one #4 mat, maximum 12 in centers in each direction and 2 in of edge cover. Available stock is 20 ft long.

Inputs

Measurement system
ft
ft
in
Center to center for bars running along Y.
in
Center to center for bars running along X.
in
ft
Common stock lengths are 20 ft and 6 m. Set the length your supplier carries.
d
Use the lap from the structural drawings when available.
SLAB REBAR MATPlan of bar runs, clear cover, and the two spacing directions. SLAB REBAR MAT X 24 ftY 24 ft#4 · 25 along X · 25 along Y50 lapsGrid lines sampled

Estimate

Rebar weight incl. laps
846.13 lb
  • Counts assume one straight mat. Confirm cover, development, stagger and lap with the structural drawings.
Weight · equivalent
383.8 kg
Continuous grid runs
50
Runs along X
25
Runs along Y
25
Actual X center spacing
11.81 in
Actual Y center spacing
11.81 in
Lap per splice
20 in
Lap joints
50
Stock pieces before offcut reuse
100
Grid intersections
625
Length before laps
1,183.33 ft
Cut length incl. laps
1,266.667 ft
Cut length · equivalent
386.08 m
Download

Working this example

Starting estimate 846.13 lbRebar weight incl. laps

Write a cut list before ordering. The runs exceed one stock length, and the offcuts may serve other straight runs.

See the calculator formulas and assumptions

Questions & answers

Why do 24 ft at 12 in centers give 25 runs each way in this garage?

After cover, the centerline span is just under 24 ft. Meeting a 12 in maximum needs 24 intervals and 25 bar runs.

How many laps does each 24 ft garage run use with 20 ft stock?

Each clear run is longer than 20 ft but shorter than two sticks joined with the 20 in lap, so it takes one splice.