ConcreteEarthLab

Worked example

Asymmetric spacing for a 48 × 30 ft shop mat

A shop mat uses #5 bars over 48 × 30 ft. The bar counts differ because the spacing limits and mat dimensions differ by axis.

Inputs

Measurement system
ft
ft
in
Center to center for bars running along Y.
in
Center to center for bars running along X.
in
ft
Common stock lengths are 20 ft and 6 m. Set the length your supplier carries.
d
Use the lap from the structural drawings when available.
SLAB REBAR MATPlan of bar runs, clear cover, and the two spacing directions. SLAB REBAR MAT X 48 ftY 30 ft#5 · 24 along X · 49 along Y97 lapsGrid lines sampled

Estimate

Rebar weight incl. laps
2,907.45 lb
  • Counts assume one straight mat. Confirm cover, development, stagger and lap with the structural drawings.
Weight · equivalent
1,318.8 kg
Continuous grid runs
73
Runs along X
24
Runs along Y
49
Actual X center spacing
11.86 in
Actual Y center spacing
15.36 in
Lap per splice
25 in
Lap joints
97
Stock pieces before offcut reuse
170
Grid intersections
1,176
Length before laps
2,585.5 ft
Cut length incl. laps
2,787.583 ft
Cut length · equivalent
849.655 m
Download

Working this example

Starting estimate 2,907.45 lbRebar weight incl. laps

Review the run table by direction before transferring quantities to the bar schedule. Check the lap staggering and joint plan.

See the calculator formulas and assumptions

Questions & answers

Why are there more continuous Y runs than X runs for this shop?

Y-running bars are counted across the longer 48 ft dimension at 12 in maximum. X-running bars are counted across 30 ft at 16 in maximum.

How many stock segments can one 48 ft shop run require?

The clear length exceeds the coverage of two 20 ft sticks with a 25 in lap. Three segments supply the run under these assumptions.