Worked example · Tray hydraulics
Foaming-service derating
Size the net vapor area and shell diameter, then compare jet-flood approach at a candidate shell ID.
A foaming service uses a 0.68 system factor at the same tray spacing and density basis.
- Flood speed
- 0.8949 m/s
- Required ID
- 2.191 m
- % flood
- 73 %
- Net area
- 3.317 m²
Crossflow tray and downcomer
Live schematicVelocity is below the screening threshold at the entered load.
Calculation inputs
- Liquid density ρL
- 790 kg/m³
- Vapor density ρV
- 4.2 kg/m³
- Surface tension σ
- 18 mN/m
- Liquid / vapor mass ratio
- 0.9
- Tray spacing TS
- 600 mm
- Foaming / system factor
- 0.68
- Downcomer area
- 12 %
- Vapor flow Qv
- 7,800 Am³/h
- Design flood target
- 73 %
- Check shell ID
- 0 m
Worked solution
- Correct the Fair capacity
The flow parameter is 0.06562. The reference factor 0.09826 m/s becomes 0.06543 m/s after tension and system corrections.
- Convert vapor load to area
The density term gives Uf = 0.8949 m/s. Divide the vapor flow in m³/s by Uf and the target fraction. The net area is 3.317 m² and the total area is 3.769 m².
- Check the shell
The required ID is 2.191 m. At the checked ID of 2.191 m, the flood approach is 73 % with 12 pp to the 85% marker.
The system factor multiplies Fair capacity before the area calculation. The derivation uses SI units.
| Fair flow parameter FLV | 0.06562 |
|---|---|
| Fair capacity factor at reference tension | 0.09826 m/s |
| Corrected capacity factor Csb | 0.06543 m/s |
| Required total shell area | 3.769 m² |
| Checked shell ID | 2.191 m |
| Checked net vapor area | 3.317 m² |
| Checked downcomer area | 0.4523 m² |
| Operating net vapor velocity | 0.6533 m/s |
| Margin to 80% flood | 7 pp |
| Margin to 85% flood | 12 pp |
Calculation inputs
Live updates
Equations and assumptions
- Fair chart fit
- FLV = (L/V)√(ρV/ρL)
- Corrected capacity
- Csb = C20 · (σ/20)^0.2 · SF
- Flood velocity
- Uf = Csb √[(ρL − ρV)/ρV]
- Area basis
- At = Qv / [Uf · target · (1 − Ad/At)]
The Lygeros–Magoulas fit to Fair data uses tray spacing in meters and the reference surface tension of 20 mN/m. Apply the system factor to account for foaming or service derating.
The meter marks 80% of predicted jet flood. The 80–85% operating band is a screening range. Downcomer area is reserved in the net-area calculation. Detailed backup, froth height, weeping and entrainment need tray hardware data.