Worked example · Pull replenishment

Stamped bracket inventory turns

Estimate annual turns and reserve for a bracket supermarket with four bins and 250 operating days.

Cards = ceil(Demand × Lead time × (1 + Buffer) ÷ Bin qty)

Baseline reading

Annual usage is 50,000 brackets. Dividing by modeled average stock of 195 gives about 256 annual turns within this specific loop.

What to test

Compare turns only across matching inventory boundaries. A full plant inventory report may also account for raw coil, finished stock, and material in transit.

Currency labels entered amounts. Exports record the selected display units.

Inputs

Replenishment loop
units/day
day
%

A 10–30% planning range is common. Check variability and upstream service.

Inventory economics
$

Results

Kanban cards or containers
4
Maximum loop units
320
Modeled average WIP
195 units
Kanban loop and reserve
Kanban loop and reserve Stock draws down from full containers to the safety and rounding reserve before replenishment. The bottom row represents the card loop. LEAD-TIME DRAWDOWN4 BINSFull stockReplenish701234Card loop
Lead-time demand
250 units
Requested safety stock
37.5 units
Reserve after container rounding
70 units
Annual inventory turns
256.41×
Average capital in loop
$159.90
Maximum capital in loop
$262.40

Model notes

Lead time starts when consumption sends the signal and ends when replenished stock can be used. Keep demand days and lead-time days on the same operating calendar.

The average models a straight drawdown from full inventory to the remaining reserve during a lead-time cycle. Use actual stock history to check inventory turns.

View the equations

Frequently asked questions

Why are the bracket loop turns higher than warehouse turns?

The bracket calculation covers only this short replenishment loop. Warehouse turns use a different stock base and may cover a broader set of items.

Should statutory holidays reduce bracket operating days?

Use the days when this loop consumes at the entered average rate. Apply the same operating-day convention to lead time.