Worked example · Pull replenishment
Two-bin fastener replenishment
Size a fastener loop for 120 pieces per day, half-day replenishment, and 40-piece bins.
Cards = ceil(Demand × Lead time × (1 + Buffer) ÷ Bin qty)
Baseline reading
Lead-time consumption is 60 fasteners. Adding 20% calls for 72 units, so two 40-piece bins cover the stated requirement.
What to test
Confirm that replenishment begins when the operative signal actually leaves the station. Audit the lead time at the bin location, including transport.
Worksheet inputs
Inputs
Results
- Kanban cards or containers
- 2
- Maximum loop units
- 80
- Modeled average WIP
- 50 units
- Lead-time demand
- 60 units
- Requested safety stock
- 12 units
- Reserve after container rounding
- 20 units
- Annual inventory turns
- 600×
- Average capital in loop
- $9.00
- Maximum capital in loop
- $14.40
Model notes
Lead time starts when consumption sends the signal and ends when replenished stock can be used. Keep demand days and lead-time days on the same operating calendar.
The average models a straight drawdown from full inventory to the remaining reserve during a lead-time cycle. Use actual stock history to check inventory turns.
Frequently asked questions
When should the operator send the fastener replenishment card?
Set a physical trigger that leaves the intended demand and reserve available during replenishment, and train the operator on that trigger.
Should open fastener bags count toward a 40-piece bin?
Count usable pieces in the defined container. Verify bin quantity at replenishment and prevent partial fills from circulating unrecorded.