Tangent and curve controls
- PVC
- 18+30.000ftUS
- PVC elevation
- 204.8ftUS
- PVI
- 19+50.000ftUS
- PVI tangent elevation
- 200ftUS
- PVT
- 21+30.000ftUS
- PVT elevation
- 203.6ftUS
- Grade difference A
- 6%
- Tightest local K
- 33.33333ftUS/%
- Low point station
- 19+80.000ftUS
- Low point elevation
- 202.1ftUS
- Turning point grade
- 0%
Parabola join at PVI station
- PVC to PVI
- 120ftUS
- PVI to PVT
- 180ftUS
- Curve elevation at join
- 202.16ftUS
- Common grade
- −0.4%
- Entering K
- 33.33333ftUS/%
- Exiting K
- 75ftUS/%
Stopping sight distance check
- Required sight distance S
- 250ftUS
- Conservative screening K
- 49.10617ftUS/%
- Check
- Review sight line
Profile elevations and grades
| Point | StationftUS | Offset from PVCftUS | ElevationftUS | Grade% |
|---|---|---|---|---|
| PVC | 18+30.000 | 0 | 204.8 | −4 |
| Stake | 18+50.000 | 20 | 204.06 | −3.4 |
| Stake | 19+00.000 | 70 | 202.735 | −1.9 |
| Join | 19+50.000 | 120 | 202.16 | −0.4 |
| Low point | 19+80.000 | 150 | 202.1 | 0 |
| Stake | 20+00.000 | 170 | 202.12667 | 0.26667 |
| Stake | 20+50.000 | 220 | 202.42667 | 0.93333 |
| Stake | 21+00.000 | 270 | 203.06 | 1.6 |
| PVT | 21+30.000 | 300 | 203.6 | 2 |
Worked check
The 120 ftUS entering section reaches −0.4% at the join. The grade reaches zero 30 ftUS into the second parabola, making the low point 19+80 at elevation 202.1 ftUS.
- Grade at parabola join (%)
- −0.4
- Low-point offset (ftUS)
- 150
- Low-point chainage (ftUS)
- 1,980
- Low-point elevation (ftUS)
- 202.1
These checks describe the original example. Reset restores the original inputs.
Formulas and conventions
Build the symmetric profile
A = g₂ − g₁ · z(x) = zPVC + g₁x ÷ 100 + Ax² ÷ (200L)
PVC and PVT are L/2 either side of the tangent intersection PVI. Grades are entered in percent. When grades have opposite signs, x = −g₁L/A is the interior turning point and its slope is exactly zero.
Join unequal tangents
gⱼ = (L₁g₁ + L₂g₂) ÷ L · zⱼ = zPVI + A L₁ L₂ ÷ (200L)
L₁ is PVC to PVI and L₂ is PVI to PVT. Each parabola integrates a linear grade between the endpoint and common join grade. Find the zero grade on the piece where the signs change. The local K values are L₁/|gⱼ − g₁| and L₂/|g₂ − gⱼ|.
Calculate the curvature rate
K = L ÷ |A|
K is length per percentage point of grade change. Equal grades form a straight tangent and have no finite K. Station labels use 100-foot stations or kilometer plus meters, depending on the working unit.
Compare the SSD geometry
Lmin = |A| S² ÷ C when Lmin ≥ S · otherwise max(0, 2S − C ÷ |A|)
For a crest, C = 200(√h₁ + √h₂)², with eye height 3.5 ft and object height 2 ft. For a sag, C = 200(h + S tan 1°), with headlight height 2 ft. The two minimum-length branches apply to equal tangents. Unequal tangents use a sufficient screen: both local K values must meet S²/C. If either is tighter, check the complete sight line. Use the adopted agency criteria and drainage controls.
More worked examples
Open a case to edit its inputs and compare the original checks.
- Symmetric metric crest high point
Solve a symmetric 2% to −2% crest and check the high point at midcurve.
- Symmetric −3% to +3% sag
Find the low point and compare its curvature rate with a required sight distance.
- Rising crest without a high point inside
Distinguish a crest in grade change from a crest with an interior summit.
- Short-curve stopping sight distance
Apply the short-curve branch when the required sight distance exceeds the curve length.
- Equal grades give a straight tangent
Check elevation stationing when both grades are the same.
GeoSurveyLab · Field calculation
Asymmetric sag in U.S. survey feet
Review sight line
Field inputs
- Working unit
- U.S. survey foot (ftUS)
- Tangent lengths
- Unequal tangent lengths
- Entering grade g₁
- -4 %
- Exiting grade g₂
- 2 %
- PVI station
- 19+50 ftUS
- PVI elevation
- 200 ftUS
- Curve length
- 300 ftUS
- Stake interval
- 50 ftUS
- PVC to PVI length
- 120 ftUS
- Required sight distance
- 250 ftUS
Tangent and curve controls
- PVC
- 18+30.000ftUS
- PVC elevation
- 204.8ftUS
- PVI
- 19+50.000ftUS
- PVI tangent elevation
- 200ftUS
- PVT
- 21+30.000ftUS
- PVT elevation
- 203.6ftUS
- Grade difference A
- 6%
- Tightest local K
- 33.3333ftUS/%
- Low point station
- 19+80.000ftUS
- Low point elevation
- 202.1ftUS
- Turning point grade
- 0%
Parabola join at PVI station
- PVC to PVI
- 120ftUS
- PVI to PVT
- 180ftUS
- Curve elevation at join
- 202.16ftUS
- Common grade
- −0.4%
- Entering K
- 33.3333ftUS/%
- Exiting K
- 75ftUS/%
Stopping sight distance check
- Required sight distance S
- 250ftUS
- Conservative screening K
- 49.1062ftUS/%
- Check
- Review sight line
Profile elevations and grades
| Point | StationftUS | Offset from PVCftUS | ElevationftUS | Grade% |
|---|---|---|---|---|
| PVC | 18+30.000 | 0 | 204.8 | −4 |
| Stake | 18+50.000 | 20 | 204.06 | −3.4 |
| Stake | 19+00.000 | 70 | 202.735 | −1.9 |
| Join | 19+50.000 | 120 | 202.16 | −0.4 |
| Low point | 19+80.000 | 150 | 202.1 | 0 |
| Stake | 20+00.000 | 170 | 202.1267 | 0.2667 |
| Stake | 20+50.000 | 220 | 202.4267 | 0.9333 |
| Stake | 21+00.000 | 270 | 203.06 | 1.6 |
| PVT | 21+30.000 | 300 | 203.6 | 2 |