How the estimate works
- Divide the signed drop by the horizontal run in matching units. Multiply by 100 for percent grade or use the arctangent for degrees.
- Subtract the cross-sectional area displaced by the pipe from the trench’s stone section. Multiply by the sloped length, then add the order allowance.
- Estimate the fabric cut width from the trench perimeter plus the lap. Use that width times the drain length for one continuous wrap.
Questions and answers
Which measurement goes in the horizontal run field for grade?
Use the level plan distance between the start and end. A tape pulled along the ground on a steep slope measures a longer distance.
What does a negative yard grade toward an outlet mean?
The entered outlet end is higher than the start. Check the surveyed ends and measure the proposed pipe inverts separately for gravity drainage.
Does a French drain stone estimate allow for the pipe taking up space?
Yes. It subtracts a cylinder using the actual outside diameter and assumes the pipe stays within the modeled stone section.