8 psig tray deaerator

A tray unit receives 2,800 lb/hr of cold make-up and 7,200 lb/hr of warm condensate with a 0.2% vent-to-liquid ratio.

Inputs

lb/hr
°F
lb/hr
°F
psig
5–15 psig, equivalent to 0.345–1.034 bar g.
psig
%
%
Tray deaerator mass and enthalpy balance
Tray deaerator mass and enthalpy balancePEGGING 818.2 lb/hr. FEEDWATER 10.8K lb/hr. SAT TEMP 234.72 °F. FIRING RELIEF 1.049 MMBtu/hPEGGING818.2lb/hrFEEDWATER10.8Klb/hrSAT TEMP234.72°FFIRING RELIEF1.049MMBtu/hDEAERATOR TRAYSMAKE-UP WATERCONDENSATEVENT VAPORPEGGING STEAMFEEDWATER OUTPegging steam / external inlet mass8.18%0%Inlet heating burden25% scale
Live steam / heatCondensate / waterDischarge / loss

Calculation results

Mixed inlet temperature
156.21°F
Deaerator saturation temperature
234.72°F
Pegging steam required
818.2lb/hr
Liquid feedwater outlet
10,796.6lb/hr
Saturated vent vapor
21.6lb/hr
Net boiler fuel-input relief
1.049MMBtu/h
Preheat credit vs all-cold baseline
1,669,891.16Btu/h
Boiler duty to generate pegging steam
809,676.95Btu/h
Mixed inlet enthalpy
124.23Btu/lb
Pegging inlet enthalpy
1,192.72Btu/lb
Feedwater outlet enthalpy
203.13Btu/lb
Vent vapor enthalpy
1,158.66Btu/lb

Check the original case

Add liquid outlet and vent vapor to match both liquid inlets plus pegging steam.

  • Pegging steam required818.2 lb/hr
  • Liquid feedwater outlet10,796.6 lb/hr
  • Deaerator saturation temperature234.72 °F
  • Net boiler fuel-input relief1.049 MMBtu/h

Formulas and assumptions

Mixed inlet

h_mix = (m_make·h_make + m_return·h_return)/(m_make + m_return)

The dry supply steam throttles at constant enthalpy. The liquid mix temperature is found by inverting the liquid enthalpy equation.

Mass and energy

h* = (h_f + r·h_g)/(1 + r); m_peg = m_in·(h* − h_mix)/(h_supply − h*)

The vent is r times liquid outlet mass, and the outlet is (m_in + m_peg)/(1 + r). Vent and liquid exit as saturated phases at the deaerator pressure. The energy and mass balances assume steady state and no shell loss.

Fuel-input relief

Net = [m_in·(h_f − h_make) − m_peg·(h_supply − h_f)]/η

Compare at equal external water inflow against an all-cold baseline. The credit includes hot return and subtracts the boiler duty required for pegging. Use site venting and dissolved oxygen requirements for commissioning.

Worked examples

Open a case to edit its inputs.