15 psig with 90% hot return

A large process plant sends 90% hot return to a 15 psig deaerator.

Inputs

lb/hr
°F
lb/hr
°F
psig
5–15 psig, equivalent to 0.345–1.034 bar g.
psig
%
%
Tray deaerator mass and enthalpy balance
Tray deaerator mass and enthalpy balancePEGGING 900.2 lb/hr. FEEDWATER 20.71K lb/hr. SAT TEMP 249.72 °F. FIRING RELIEF 3.338 MMBtu/hPEGGING900.2lb/hrFEEDWATER20.71Klb/hrSAT TEMP249.72°FFIRING RELIEF3.338MMBtu/hDEAERATOR TRAYSMAKE-UP WATERCONDENSATEVENT VAPORPEGGING STEAMFEEDWATER OUTPegging steam / external inlet mass4.54%0%Inlet heating burden25% scale
Live steam / heatCondensate / waterDischarge / loss

Calculation results

Mixed inlet temperature
207.42°F
Deaerator saturation temperature
249.72°F
Pegging steam required
900.2lb/hr
Liquid feedwater outlet
20,710.7lb/hr
Saturated vent vapor
31.1lb/hr
Net boiler fuel-input relief
3.338MMBtu/h
Preheat credit vs all-cold baseline
3,614,593.4Btu/h
Boiler duty to generate pegging steam
877,152.58Btu/h
Mixed inlet enthalpy
175.61Btu/lb
Pegging inlet enthalpy
1,192.72Btu/lb
Feedwater outlet enthalpy
218.33Btu/lb
Vent vapor enthalpy
1,163.94Btu/lb

Check the original case

Compare net firing relief with the all-make-up case. The output accounts for steam spent on pegging.

  • Pegging steam required900.2 lb/hr
  • Liquid feedwater outlet20,710.7 lb/hr
  • Deaerator saturation temperature249.72 °F
  • Net boiler fuel-input relief3.338 MMBtu/h

Formulas and assumptions

Mixed inlet

h_mix = (m_make·h_make + m_return·h_return)/(m_make + m_return)

The dry supply steam throttles at constant enthalpy. The liquid mix temperature is found by inverting the liquid enthalpy equation.

Mass and energy

h* = (h_f + r·h_g)/(1 + r); m_peg = m_in·(h* − h_mix)/(h_supply − h*)

The vent is r times liquid outlet mass, and the outlet is (m_in + m_peg)/(1 + r). Vent and liquid exit as saturated phases at the deaerator pressure. The energy and mass balances assume steady state and no shell loss.

Fuel-input relief

Net = [m_in·(h_f − h_make) − m_peg·(h_supply − h_f)]/η

Compare at equal external water inflow against an all-cold baseline. The credit includes hot return and subtracts the boiler duty required for pegging. Use site venting and dissolved oxygen requirements for commissioning.

Worked examples

Open a case to edit its inputs.