Worked example · Hydrology

Interchange ramp and embankment runoff

A steep roadway ramp sheds runoff across an embankment and into a roadside channel. Use the path grade along the channel for Kirpich.

Inputs

Land cover
SurfaceArea (acre)C
Pavement
0–200 acre
0–1
Landscape
0–200 acre
0–1
Open ground
0–200 acre
0–1

Enter area and runoff coefficient for up to three surface categories. Set unused areas to zero.

Design storm
0–25 in/hr

Read intensity for the selected return period and duration from your local IDF data.

Kirpich flow path
10–20,000 ft
0.05–40 %

Use the longest hydraulic channel path and its average grade.

Catchment plan

Live results
Catchment plan Composite runoff estimate. Use rainfall intensity from the local IDF curve at the adopted design duration. PEAK FLOW 7.02 cfs COMPOSITE C 0.61 DRAINAGE AREA 1.84 acre KIRPICH T꜀ 2.86 min DivideOutfallPath · 540 ft 0 · no runoffComposite C1 · full runoff

Composite runoff estimate

Use rainfall intensity from the local IDF curve at the adopted design duration.

Calculation results

Peak flow
7.02 cfs
Composite C
0.61
Drainage area
1.84 acre
Kirpich t꜀
2.86 min
US-equivalent flow factor
1.00833

Worked calculation

Double the path length to see how the 0.77 exponent affects travel time. Keep the Rational discharge inputs fixed for the comparison.

C = Σ(Aᵢ Cᵢ) / ΣAᵢ · Q = C i A × K · t꜀ = 0.0078 L⁰·⁷⁷ S⁻⁰·³⁸⁵ in minutes with L in ft.

The exact US factor is 121/120 and is displayed as 1.0083. SI uses Q = C i A / 360 with i in mm/hr and A in ha. The rounded US convention uses 1.000. Kirpich estimates the channel travel component. Add sheet and shallow concentrated travel where applicable, and verify local minimum durations and area limits.