Outgassing & leak budget / Worked example

Kapton Cable Bundle in High Vacuum

A dense cable bundle exposes 0.065 m² of Kapton inside a 2.1 m² baked chamber.

Readout ↓

Inputs

Pressure target and fixed loads
Pa
L/s
Pa·m³/s
Pa·m³/s
Chamber surface 1
m²
Pa·m³/(s·m²)
Chamber surface 2
m²
Pa·m³/(s·m²)
Chamber surface 3
Chamber surface 4
Chamber surface 5
Chamber surface 6

Live readout

Base pressure above target
Total load6.621e-6Pa·m³/sNeeded speed1104L/sBase pressure4.138e-5PaSpeed reserve-589.7%Gas load by sourceChamberSurface 298.2%O-ring1.21%Surface 10.317%He leak0.302%Speed demand / available speedDemand1100 L/sAvailable160 L/sReserve-590%
Total gas load
6.621e-6 Pa·m³/s
Required effective speed
1104 L/s
Predicted base pressure
4.138e-5 Pa
Candidate speed reserve
-589.7%

Gas load ranking

SourceGas loadShare
Surface 2Kapton 6.5e-6 Pa·m³/s 98.17%
O-ringO-ring permeation 8e-8 Pa·m³/s 1.208%
Surface 1316L, baked 24 h at 150 °C 2.1e-8 Pa·m³/s 0.3172%
He leakHelium leak allowance 2e-8 Pa·m³/s 0.3021%

    Reading this example

    The small polymer area can dominate the load. Compare a measured material rate before deciding whether to change routing or pump speed.

    Model & assumptions

    Material load

    Qₜ = Σ Aᵢqᵢ + Qₚₑᵣₘ + Qₗ

    Use exposed surface area and the specific rate at the same time, temperature and conditioning state. Add steady permeation and the leak allowance as separate loads.

    Pressure and speed

    P = Qₜ/Sₑ · Sᵣₑq = Qₜ/Pₜ

    The Pareto list ranks each contributing load by its fraction of the total. Speed reserve is 1 − Sᵣₑq/Sₑ, using candidate chamber-effective speed.