Double FCAW fillets on a beam stiffener run

Two 8 mm fillets run along a batch of stiffeners with 18 m of seam on each side.

Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.

Inputs

Joint geometry
mm
m
Use length per side for a double fillet.
%
Process & costing
kg/m³
kg/h
%
USD/kg
USD/h
USD

Live weld sheet

Updated from inputs
Weld cross-sectionFilled cross-section 71.68 mm². Filler to purchase 12.352 kg. Arc-on time 148.22 min. Filler and labor cost 516.65 USD WELD AREA71.68mm²PURCHASED12.352kgARC TIME148.22minTOTAL COST516.65USD WELD CROSS-SECTION Leg 8 mmSeam 18 mDouble fillet COST ALLOWANCEFAIL
Outside screen

Cost allowance · Filler + labor vs 260 USD.

Result details

Filled cross-section71.68 mm²
Filler to purchase12.352 kg
Arc-on time148.22 min
Filler and labor cost516.65 USD
Base weld section64 mm²
Deposited volume1,290.24 cm³
Theoretical deposited mass10.128 kg
Consumable loss2.223 kg
Deposition efficiency82 %
Net deposition rate4.1 kg/h
Gross consumption rate5 kg/h
Paid shop time423.49 min
Filler cost79.05 USD
Labor cost437.6 USD
Budget margin-256.65 USD

Worked example

Starting inputs

Weld profile
Double fillet
Equal leg size
8 mm
Seam length
18 m
Extra weld area
12 %
Welding process
FCAW
Net deposition rate
4.1 kg/h
Cost allowance
260 USD

Baseline results

Filled cross-section
71.68 mm²
Filler to purchase
12.352 kg
Arc-on time
148.22 min
Filler and labor cost
516.65 USD

A filled section of 71.68 mm² over 18 m deposits 10.128 kg. At 82 % process yield, allow 12.352 kg of consumables.

Try it. Change from a 35% to a 50% arc-on factor. Paid hours fall while deposited mass and arc minutes stay fixed.

Calculation method

A = A₀(1 + r) · m = ρAL · mᵦ = m / ηd

An equal-leg fillet starts at w²/2 per side. A symmetric single V has section g·t + (t − f)²·tan(α/2). A balanced double V halves the bevel term at the same total root face. For a single bevel, use g·t + ½(t − f)²·tan(β). Reinforcement adds the entered percentage to the full base section.

The model assumes uniform density and a constant net deposition rate. Divide deposited mass by the process yield to estimate purchases. Divide arc-on time by the arc-on factor to obtain paid shop time. The cost screen compares filler plus labor against your allowance. Add gas, flux, setup or handling to your estimate separately.