WeldMetalLab

Consumable estimating

One-sided bevel with GMAW

Only one member can be beveled on this assembly. Enter 45° for the prepared edge and leave the opposite edge square.

Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.

Inputs

Joint geometry
mm
mm
mm
°
Included angle for V grooves. Use the angle on the prepared edge for a single bevel.
m
Use length per side for a double fillet.
%
Process & costing
kg/m³
kg/h
%
USD/kg
USD/h
USD

Live weld sheet

Updated from inputs
Weld cross-sectionFilled cross-section 92.88 mm². Filler to purchase 6.34 kg. Arc-on time 99.99 min. Filler and labor cost 335.79 USD WELD AREA92.88mm²PURCHASED6.34kgARC TIME99.99minTOTAL COST335.79USD WELD CROSS-SECTION Plate 12 mmGap 3 mmSingle bevel COST ALLOWANCEFAIL
Outside screen

Cost allowance · Filler + labor vs 150 USD.

Result details

Filled cross-section92.88 mm²
Filler to purchase6.34 kg
Arc-on time99.99 min
Filler and labor cost335.79 USD
Base weld section86 mm²
Deposited volume743.04 cm³
Theoretical deposited mass5.833 kg
Consumable loss0.507 kg
Deposition efficiency92 %
Net deposition rate3.5 kg/h
Gross consumption rate3.8 kg/h
Paid shop time285.69 min
Filler cost40.58 USD
Labor cost295.21 USD
Budget margin-185.79 USD

Worked example

Starting inputs

Weld profile
Single bevel groove
Plate thickness
12 mm
Root gap
3 mm
Total root face
2 mm
Groove angle
45 °
Seam length
8 m
Extra weld area
8 %

Baseline results

Filled cross-section
92.88 mm²
Filler to purchase
6.34 kg
Arc-on time
99.99 min
Filler and labor cost
335.79 USD

A filled section of 92.88 mm² over 8 m deposits 5.833 kg. At 92 % process yield, allow 6.34 kg of consumables.

Try it. Changing the root gap adds a strip across the full plate section. Angle changes affect just the tapered part of the bevel.

Calculation method

A = A₀(1 + r) · m = ρAL · mᵦ = m / ηd

An equal-leg fillet starts at w²/2 per side. A symmetric single V has section g·t + (t − f)²·tan(α/2). A balanced double V halves the bevel term at the same total root face. For a single bevel, use g·t + ½(t − f)²·tan(β). Reinforcement adds the entered percentage to the full base section.

The model assumes uniform density and a constant net deposition rate. Divide deposited mass by the process yield to estimate purchases. Divide arc-on time by the arc-on factor to obtain paid shop time. The cost screen compares filler plus labor against your allowance. Add gas, flux, setup or handling to your estimate separately.

References

More worked examples