Consumable estimating
One-sided bevel with GMAW
Only one member can be beveled on this assembly. Enter 45° for the prepared edge and leave the opposite edge square.
Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.
Inputs
Live weld sheet
Updated from inputsCost allowance · Filler + labor vs 150 USD.
Result details
| Filled cross-section | 92.88 mm² |
|---|---|
| Filler to purchase | 6.34 kg |
| Arc-on time | 99.99 min |
| Filler and labor cost | 335.79 USD |
| Base weld section | 86 mm² |
| Deposited volume | 743.04 cm³ |
| Theoretical deposited mass | 5.833 kg |
| Consumable loss | 0.507 kg |
| Deposition efficiency | 92 % |
| Net deposition rate | 3.5 kg/h |
| Gross consumption rate | 3.8 kg/h |
| Paid shop time | 285.69 min |
| Filler cost | 40.58 USD |
| Labor cost | 295.21 USD |
| Budget margin | -185.79 USD |
Worked example
Starting inputs
- Weld profile
- Single bevel groove
- Plate thickness
- 12 mm
- Root gap
- 3 mm
- Total root face
- 2 mm
- Groove angle
- 45 °
- Seam length
- 8 m
- Extra weld area
- 8 %
Baseline results
- Filled cross-section
- 92.88 mm²
- Filler to purchase
- 6.34 kg
- Arc-on time
- 99.99 min
- Filler and labor cost
- 335.79 USD
A filled section of 92.88 mm² over 8 m deposits 5.833 kg. At 92 % process yield, allow 6.34 kg of consumables.
Try it. Changing the root gap adds a strip across the full plate section. Angle changes affect just the tapered part of the bevel.
Calculation method
A = A₀(1 + r) · m = ρAL · mᵦ = m / ηd
An equal-leg fillet starts at w²/2 per side. A symmetric single V has section g·t + (t − f)²·tan(α/2). A balanced double V halves the bevel term at the same total root face. For a single bevel, use g·t + ½(t − f)²·tan(β). Reinforcement adds the entered percentage to the full base section.
The model assumes uniform density and a constant net deposition rate. Divide deposited mass by the process yield to estimate purchases. Divide arc-on time by the arc-on factor to obtain paid shop time. The cost screen compares filler plus labor against your allowance. Add gas, flux, setup or handling to your estimate separately.