Single GMAW fillet on clip angles

Twenty feet of clip-angle seam use one 3/16 in equal-leg fillet. Price the solid wire and paid time together.

Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.

Inputs

Joint geometry
in
ft
Use length per side for a double fillet.
%
Process & costing
lb/in³
lb/h
%
USD/lb
USD/h
USD

Live weld sheet

Updated from inputs
Weld cross-sectionFilled cross-section 0.018 in². Filler to purchase 1.365 lb. Arc-on time 13.15 min. Filler and labor cost 49.26 USD WELD AREA0.018in²PURCHASED1.365lbARC TIME13.15minTOTAL COST49.26USD WELD CROSS-SECTION Leg 0.188 inSeam 20 ftSingle fillet COST ALLOWANCEPASS
Pass · within screen

Cost allowance · Filler + labor vs 90 USD.

Result details

Filled cross-section0.018 in²
Filler to purchase1.365 lb
Arc-on time13.15 min
Filler and labor cost49.26 USD
Base weld section0.018 in²
Deposited volume4.43 in³
Theoretical deposited mass1.256 lb
Consumable loss0.109 lb
Deposition efficiency92 %
Net deposition rate5.73 lb/h
Gross consumption rate6.23 lb/h
Paid shop time43.83 min
Filler cost3.96 USD
Labor cost45.29 USD
Budget margin40.74 USD

Worked example

Starting inputs

Weld profile
Single fillet
Equal leg size
0.1875 in
Seam length
20 ft
Extra weld area
5 %
Welding process
GMAW
Net deposition rate
5.732019 lb/h
Arc-on factor
30 %

Baseline results

Filled cross-section
0.018 in²
Filler to purchase
1.365 lb
Arc-on time
13.15 min
Filler and labor cost
49.26 USD

A filled section of 0.018 in² over 20 ft deposits 1.256 lb. At 92 % process yield, allow 1.365 lb of consumables.

Try it. Try two fillet sides at the same seam length. With every other input fixed, the deposited and purchased quantities double.

Calculation method

A = A₀(1 + r) · m = ρAL · mᵦ = m / ηd

An equal-leg fillet starts at w²/2 per side. A symmetric single V has section g·t + (t − f)²·tan(α/2). A balanced double V halves the bevel term at the same total root face. For a single bevel, use g·t + ½(t − f)²·tan(β). Reinforcement adds the entered percentage to the full base section.

The model assumes uniform density and a constant net deposition rate. Divide deposited mass by the process yield to estimate purchases. Divide arc-on time by the arc-on factor to obtain paid shop time. The cost screen compares filler plus labor against your allowance. Add gas, flux, setup or handling to your estimate separately.