Consumable estimating
Stainless GMAW filler purchase quote
A series of stainless butt joints has 22 m of seam. Use the stainless wire price and density from the shop estimate.
Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.
Inputs
Live weld sheet
Updated from inputsCost allowance · Filler + labor vs 210 USD.
Result details
| Filled cross-section | 53.936 mm² |
|---|---|
| Filler to purchase | 10.254 kg |
| Arc-on time | 235.83 min |
| Filler and labor cost | 703.06 USD |
| Base weld section | 49.032 mm² |
| Deposited volume | 1,186.58 cm³ |
| Theoretical deposited mass | 9.433 kg |
| Consumable loss | 0.82 kg |
| Deposition efficiency | 92 % |
| Net deposition rate | 2.4 kg/h |
| Gross consumption rate | 2.61 kg/h |
| Paid shop time | 501.77 min |
| Filler cost | 184.57 USD |
| Labor cost | 518.5 USD |
| Budget margin | -493.06 USD |
Worked example
Starting inputs
- Weld profile
- Single V groove
- Plate thickness
- 8 mm
- Root gap
- 2.2 mm
- Total root face
- 1.3 mm
- Groove angle
- 70 °
- Seam length
- 22 m
- Welding process
- GMAW
Baseline results
- Filled cross-section
- 53.936 mm²
- Filler to purchase
- 10.254 kg
- Arc-on time
- 235.83 min
- Filler and labor cost
- 703.06 USD
A filled section of 53.936 mm² over 22 m deposits 9.433 kg. At 92 % process yield, allow 10.254 kg of consumables.
Try it. Adjust the filler price while keeping geometry fixed. Only the filler cost, total cost and budget margin move.
Calculation method
A = A₀(1 + r) · m = ρAL · mᵦ = m / ηd
An equal-leg fillet starts at w²/2 per side. A symmetric single V has section g·t + (t − f)²·tan(α/2). A balanced double V halves the bevel term at the same total root face. For a single bevel, use g·t + ½(t − f)²·tan(β). Reinforcement adds the entered percentage to the full base section.
The model assumes uniform density and a constant net deposition rate. Divide deposited mass by the process yield to estimate purchases. Divide arc-on time by the arc-on factor to obtain paid shop time. The cost screen compares filler plus labor against your allowance. Add gas, flux, setup or handling to your estimate separately.