Worked example · Vibrating Screen

Dry limestone top deck

A top deck classifies limestone with 68% undersize in the feed. The aperture is three-quarters of an inch.

Live results

Screen deck and material split

Edit inputs
Screen deck and material split Four live readings and a schematic of the selected material-handling configuration. Full values follow the diagram. DECK AREA87.46ft²PASS EFF.89.05%UNDERSIZE145.32TPHOVERSIZE94.68TPH VIBRATING DECKMATERIAL SPLITOpening 0.75 inDry deckFeed240 TPHOversize94.68 TPHUndersize145.32 TPHTop deck Required / installed area104.12%Installed deck is below the estimated target area.

Installed deck is below the estimated target area.

All calculated values
Required live deck area
87.459ft²
Estimated passing efficiency
89.047%
Undersize product
145.324TPH
Oversize product
94.676TPH
True undersize in feed
163.2TPH
Undersize retained on deck
17.876TPH
Deck area at 90% recovery
87.459ft²
Aperture base capacity
1.878TPH/ft²
Corrected unit capacity
1.866TPH/ft²
Oversize correction
1.035
Half-size correction
0.96
Deck position correction
1
Wet screening correction
1
Density correction
1

Inputs

Unit system
Operating inputs
TPH
%
%
Percent of total feed smaller than half the selected aperture.
in
lb/ft³
ft²
%
Drive & model factors
TPH/ft²
0 uses the aperture curve. Enter the passing capacity per unit area at the stated reference conditions.

Worked solution

Starting case in US units

  1. Apply the 68% undersize fraction to the 240 TPH feed, giving 163.2 TPH of true undersize.
  2. The corrected unit capacity is 1.87 TPH/ft². The area required for 90% passing efficiency is 87.46 ft².
  3. With 84 ft² installed, predicted passing efficiency is 89.05%, splitting into 145.32 TPH passing and 94.68 TPH retained.

Try it. Compare the installed area with the computed area for 90% passing recovery and trace the two product streams.

More worked examples

Open a different starting case

Equations and assumptions

Aperture rating and corrections

C = C₀ · Fo · Fh · Fd · Fw · Fρ

The default C₀ is 2.2 × aperture(in)^0.55 short tons/h/ft². Reference conditions are 25% oversize, 40% half-size, 100 lb/ft³, top deck, dry screening and 90% recovery. Fo = 1 + 0.5(oversize fraction − 0.25), Fh = 1 + (half-size fraction − 0.40), and Fd = 1/0.9/0.8 by deck position (top/second/third respectively). Wet spray uses Fw = 1 + 0.3/(1 + aperture(in)²). Fρ scales with bulk density. The curve and corrections are illustrative VSMA-style estimates. Use an OEM rating and validate motion, media open area, bed depth and blinding before selection.

Live area and passing efficiency

A₉₀ = Qfeed · fᵤ / C   |   E = 1 − 0.1^(Ainstalled/A₉₀)
Arequired = A₉₀ · ln(1 − Etarget) / ln(0.1)

fᵤ is the fraction smaller than the aperture. This first-pass recovery curve is anchored at 90% for A₉₀. Its estimated recovery depends on the installed live area. Use a sampled and weighed feed and product mass balance to establish plant efficiency.

Stream split

Qpassing = Qfeed · fᵤ · E   |   Qretained = Qfeed − Qpassing

This model assumes coarse particles remain above the aperture. The oversize product includes unrecovered fines. Feed, passing and retained rates use the same mass basis.

References